
INTUITY CONVERSANT System Version 6.0
MAP/100 New System Installation
585-310-176
Issue 3.0
June 1997
System Installation Checklist
Page A-4
System Installation Checklist
A
11
Locate key
components on the
MAP.
2
12
Make cable
connections.
Included are
network and
asynchronous
connections.
These MUST be
made prior to
powering up
3
Chapter 3, ‘‘Making
Cable
Connections’’
13
Connect the MAP to
the power service
and power up.
4
Chapter 4,
‘‘Connecting
Peripherals and
Powering Up’’
14
Verify the system
setup screen is
correct, if necessary.
4
Chapter 4,
‘‘Connecting
Peripherals and
Powering Up’’
15
Administer modem
for remote
administration.
Systems using a
modem for
remote
administration
4
Chapter 4,
‘‘Connecting
Peripherals and
Powering Up’’
16
Administer modem(s)
on the system.
Do not use these
procedures on the
remote
maintenance
modem.
Systems using a
modem for
remote
administration
4
Chapter 4,
‘‘Connecting
Peripherals and
Powering Up’’
17
Administer the
printer.
Systems using a
printer
4
Chapter 4,
‘‘Connecting
Peripherals and
Powering Up’’
Table A-1.
MAP Hardware Installation Checklist — Pre-assembled
System —
Continued
Task
Task Description
Comments
Chapter
Section
✔
Continued on next page