Make sure the base bracket is free of debris. Then with one person at either end, lift the panel vertically and
insert into the top rebates of the post.
The first panel will have the capping channel installed so the initial 25mm will be tight to insert as the post
is trying to ‘stretch’ to accommodate the panel plus the capping channel, this is normal.
If you feel it is too tight to insert you can remove the top tek screw which will allow the post to expand more
readily. Be sure to re-install the tek screw prior to inserting the top panel.
Note: The panel must be guided down at an even & level rate or it will jam.
If your wall is 1200mm high or
lower go straight to Step 10
You won’t have to ‘double stack’ panels