BATCHEN
Issue Date 2/11/01
QMAN0043 Installers Manual CII & C2000 Rev A.doc
- 12 -
PART 5
DISPENSER INSTALLATION
WARNING
DO NOT SWITCH ON MAINS POWER TO DISPENSER BEFORE
COMPLETING PART 6.1 - INITIAL CHECK, AND PART 6.2 - DISPENSER
ELECTRONIC SETUP.
5.1 Dispenser Inspection
When the Dispenser arrives on site, the shipping carton should be removed and the
Dispenser inspected for damage. If damage is evident, it should be immediately
reported to the carrier and your local Batchen representative for insurance purposes.
5.2 Dispenser Preparation
Before commencing the installation of the dispenser at least the hydraulics cabinet
panels should be removed to prevent damage during the installation.
5.3 Dispenser Lifting
WARNING
LIFTING THE DISPENSER OTHER THAN AS DESCRIBED RISKS
SERIOUS DAMAGE TO THE DISPENSER AND PERSONNEL INVOLVED.
ON NO ACCOUNT SHOULD THE DISPENSER BE LIFTED BY PLACING A
SLING UNDER THE ELECTRONICS CABINET.
The dispenser may be lifted using a suitable forklift, crane or other mobile lifting
equipment. Lifting equipment used must have a capacity of at least 250 Kg.
*
If a forklift is to be used, the tines of the forklift should be placed through the
pallet that the dispenser is mounted on for shipping.
*
If a crane is to be used, a sling provided with a suitable protective cover to
prevent scratching should be used.
The sling should be placed under the top member of the hydraulics compartment
frame and then over the front faces of the electronics cabinet.
5.4 Positioning the Dispenser on the Dispenser Base