9252000990 Rev N
BE1-50/51M Testing
5-1
SECTION 5
•
TESTING
GENERAL
Dielectric testing, operational testing, and periodic testing are described in the following paragraphs.
DIELECTRIC TEST
In accordance with IEC 255-5 and IEEE C37.90-1989, one-minute dielectric (high potential) tests may be
performed as follows:
All circuits to ground:
2,828 Vdc.
Input to output circuits:
2,000 Vac or 2,828 Vdc.
Output contacts are surge protected.
OPERATIONAL TEST PROCEDURE
The following procedures verify operation of BE1-50/51M relays. The test setups of Figures 5-1 and
5-2 are intended primarily as an illustration of the principles involved. Other test setups known to be
capable of testing with the stated and implied tolerances (including equipment specifically designed for
testing relays) may be used.
Test Equipment Required
•
Current source with a range from 0 to 20 Aac (sensing input current)
•
Current source 0.2 to 3 Aac (target operation)
•
Timer or counter
CAUTION
When testing units with integrating reset characteristics selected, timing may be
affected by the integrating reset.
Содержание BE1-50M
Страница 1: ...INSTRUCTION MANUAL FOR OVERCURRENT RELAY BE1 50 51M Publication 9252000990 Revision N 03 08 ...
Страница 2: ......
Страница 8: ...vi BE1 50 51M Introduction 9252000990 Rev N This page intentionally left blank ...
Страница 10: ...ii BE1 50 51M General Information 9252000990 Rev N This page intentionally left blank ...
Страница 22: ...ii BE1 50 51M Controls and Indicators 9252000990 Rev N This page intentionally left blank ...
Страница 28: ...ii BE1 50 51M Functional Description 9252000990 Rev N This page intentionally left blank ...
Страница 32: ...ii BE1 50 51M Installation 9252000990 Rev N This page intentionally left blank ...
Страница 37: ...9252000990 Rev N BE1 50 51M Installation 4 5 Figure 4 5 DC Control Connections ...
Страница 38: ...4 6 BE1 50 51M Installation 9252000990 Rev N Figure 4 6 BE1 50 51M Terminal Connections Rear View ...
Страница 40: ...4 8 BE1 50 51M Installation 9252000990 Rev N This page intentionally left blank ...
Страница 42: ...ii BE1 50 51M Testing 9252000990 Rev N This page intentionally left blank ...
Страница 50: ...5 8 BE1 50 51M Testing 9252000990 Rev N This page intentionally left blank ...
Страница 52: ...ii BE1 50 51M Relay Differences 9252000990 Rev N This page intentionally left blank ...
Страница 56: ...6 4 BE1 50 51M Relay Differences 9252000990 Rev N This page intentionally left blank ...
Страница 58: ...ii BE1 50 51M Time Characteristic Curves 9252000990 Rev N This page intentionally left blank ...