Installation / Assembly
dizzer® XL Series Modules for Open Platform
– Assembly Instructions 1.1(2019-01) E inge
Page 36 of 44
© inge GmbH
5.5.1
Mounting
dizzer
®
XL Modules with a Crane
Mounting with a Crane
Step
Activity
Figure
1
Attach the module using a mounting strap (min. load capacity
of 60 kg) directly under the filtrate port and place the loop into
the crane hook.
2
Carefully lift the module using the crane.
3
Hold the module at the top connection and stabilize it
throughout the transport procedure.
4
Move the module to the installation position with a crane.
5
Lower the module so that the module connections are
arranged across from the connections on the module rack.
6
Keep the mounting strap taut so that the module cannot tip.
7
Mount the module using the procedure described in section:
→
8
Slacken the mounting strap with the crane and release it from
the crane hook and the module.