FXV3/CXVT Rigging & Assembly Instructions
–
Unit Rigging & Assembly
Page | 13
Section Assembly
NOTICE
: For weight information, refer to the submittal drawing package. Any motors or accessories shipped in
the cold-water basin must be removed prior to installing the upper (mechanical and coil casing) section.
1.
Remove any accessories shipped in the cold-water basin.
2.
Position the lower section on the unit supports and bolt in place. Refer to
on
Page 12
3.
Wipe moisture and dirt from the perimeter flange and plenum step as shown in
4.
Apply flat butyl sealer tape (BAC part #554000) across the entire plenum step seal as shown in
a.
Refer to critical seal area shown in
5.
Apply a
2”
x
2”
piece of flat butyl sealer tape to the corner rigging guides as shown in
and detailed in
6.
Apply flat butyl sealer tape around the entire perimeter of the lower section. Align the tape on the perimeter flange as shown in
See
for critical sealing areas, allow 1” overlap tape at these locations.
Figure 5. FXV3 and CXVT Lower Section
Plenum Step Seal