26 | Baker Hughes
Copyright 2023 Baker Hughes Company. All rights reserved.
1000/1500 Spring Chamber Assembly
Fasten the bottom spacer assembly to the top body assembly
(L) using six (6) fiberglass washers (N) and six (6) 1/4-20 x
3-inch SHCS (O). Bolt the spring chamber (H) into the bottom
spacer (K) using six (6) fiberglass washers (N) and six (6) 1/4-20
x 1
1
/
2
-inch SHCS (P).
Figure 12: Bolting the spring chamber
Bearing Case Assembly
For 1500-CH: Press fit the thrust bearing (A) into the bearing
case (B).
For all other CH models, press fit the thrust bearing (A) into the
bearing case (C).
Figure 13: Thrust bearing assembly
Bearing Nut Assembly (All Models)
Slide a –108 O-ring (D) onto the adjusting screw (E) (as shown in
Figure 14). Slide the bearing case assembly onto the adjusting
screw (E). Thread the aluminum bearing nut (G) onto the screw
(E) from the bottom. Leave some room below the bearing nut
(G). Thread 1/2-20 SS left-hand jam nut (F) onto the screw (E).
The jam nut (F) and bearing nut (G) should be tightened against
each other as shown in Figure 15.
Figure 14: Adding aluminum bearing nut
1500
Содержание Becker VRP-CH Series
Страница 1: ...VRP CH Series Valve Regulator Pilots Instruction Manual Rev A Baker Hughes Data Classification Public...
Страница 30: ...30 Baker Hughes Copyright 2023 Baker Hughes Company All rights reserved Part Silhouettes...
Страница 34: ...34 Baker Hughes Copyright 2023 Baker Hughes Company All rights reserved Notes...