pBS2120 Base Station Installation Guide 

12 

 

open the wiring cavity. 

2.  Connect the Ethernet cable to 

ETH

 interface in the wiring cavity. 

3.  Lay Ethernet cable along the wire groove, and stretch out the wiring cavity from 

ETH

 

hole. 

4.  The other end of the Ethernet cable connects to the PoE power adaptor. 

4.3.2  Connect Ground Cable 

Make the grounding cable according the actual situation of the installation site. 

The grounding screws of pBS2120 located on the bottom of the base station, as shown 

in Figure 4-1. 

Figure 4-1 Location of Grounding Screws 

 

 

1.  Unscrew  the  grounding  screw,  connect  one  end  of  the  grounding  cable  to  the 

grounding screw, and fasten it again. 

2.  The other end of the ground cable needs to connect to a good grounding point. 

 

Содержание pBS2120

Страница 1: ...01 All rights reserved Baicells Technologies Co Ltd pBS2120 Base Station Installation Guide...

Страница 2: ...No part of this specification may be reproduced in any form or means without the prior written consent of Baicells Disclaimer This specification is preliminary and is subject to change at any time wi...

Страница 3: ...t of Box Audit 5 3 Installation Preparation 6 Support Materials 6 3 1 Installation Tools 6 3 2 Installation Environment 7 3 3 3 3 1 Locational Requirements 7 3 3 2 Environmental Requirements 7 Personn...

Страница 4: ...and operators enterprises and so on Features 1 2 Adopt the integration design of baseband and RF flexible to deploy Based on 3GPP international standard TD LTE technology provide high speed data servi...

Страница 5: ...2120 Appearance The pBS2120 interfaces and indicators are shown in Figure 1 2 Figure 1 2 pBS2120 Interfaces and Indicators The pBS2120 interfaces are described in Table 1 1 Table 1 1 pBS2120 Interface...

Страница 6: ...dware alarm e g VSWR alarm OFF No alarm Technical Specification 1 4 1 4 1 Hardware Specification Item Description LTE Mode LTE TDD LTE Frequency 3650 MHz 3700 MHz Channel Bandwidth 10 MHz 20 MHz Outpu...

Страница 7: ...ing Support Network Management Interface Support TR069 interface protocol Northbound Interface Support Web service Socket FTP and other interface modes MTBF 50000 hours MTTR 1 hour Maintenance Support...

Страница 8: ...is consistent with the requirement 2 Base station mounting bracket 1 Fixed with base station 3 Integrated bracket for on pole or on wall 1 Used for fix on pole or on wall 4 U shape clamp 1 Used for fi...

Страница 9: ...for Installing Base Station Item Description Ethernet cable Outdoor CAT6 Shorter than 100m 330 feet Ground cable 16mm yellow green wire Installation Tools 3 2 The following tools are needed during the...

Страница 10: ...ion can be chosen to meet the communication engineering environmental requirements as well as the technical requirements of network planning and communication equipment 3 3 2 Environmental Requirement...

Страница 11: ...operate the equipment This equipment has been tested and found to comply with the limits for a Class A digital device pursuant to part 15 of the FCC Rules These limits are designed to provide reasona...

Страница 12: ...aux deux conditions suivantes 1 l appareil ne doit pas produire de brouillage et 2 l utilisateur de l appareil doit accepter tout brouillage radio lectrique subi m me si le brouillage est susceptible...

Страница 13: ...r of the pole 40mm 100mm 1 As the following figure assemble the bracket for pole installation and fasten screws 2 Mounting bracket installs is complete as shown in the following figure 3 Fit the base...

Страница 14: ...12mm diameter and 80mm depth holes in the wall by following the marked locations 3 Check the up down direction of the installation rack and then fix the base station to the wall using M8 80 expansion...

Страница 15: ...ects to the PoE power adaptor 4 3 2 Connect Ground Cable Make the grounding cable according the actual situation of the installation site The grounding screws of pBS2120 located on the bottom of the b...

Страница 16: ...Table 5 1 Table 5 1 pBS2120 Indicator Description Identity Color Status Description PWR Green Steady On Power On OFF No Power Supply ACT Green Steady On The cell is activated OFF The cell is not acti...

Отзывы: