Finished Grade
3. Install anchor plate and bolt assembly flush
with the finished grade.
1 1/2”
1. Adjusted anchor bolts to project at least 1-1/2”
using the four (4) 1/4-20 nuts to the top of the
plate. The four (4) nuts can be left in place
while concrete is poured.
4. With the conduits in place and the anchor
plate properly positioned, secured and leveled,
concrete may be poured.
2. Run conduit inside of the anchor plate center
hole prior to pouring concrete.
YKB Anchor Kit Installation
5. The fixture may be installed by removing the
four (4) 1/4-20 nuts and re-using them to
secure the fixture mounting base assembly.
Trim conduit as needed.
Soil Prep
Conduit
trench
B. Dig hole 13” wide and 24” deep.
Conduit
Trench
Excavate for
anchor bolts
C. Prep soil according to DIG-IT Guide.
A. Determine Soil Type by referencing DIG-IT
Guide. Prep soil according to DIG-IT Guide.
IMPORTANT SAFETY INFORMATION LISTED ON REVERSE
READ, FOLLOW, AND SAVE ALL SAFETY AND INSTALLATION INSTRUCTIONS
40429 Brickyard Drive • Madera, CA 93636 • USA
559.438.5800 • FAX 559.438.5900
www.bklighting.com • [email protected]
B-K LIGHTING
RELEASED DATE
09/03/2021
REFERENCE NUMBER
INS-2850-00
Yukon Bollard
Installation Instructions