IMPORTANT SAFETY INFORMATION LISTED ON REVERSE
READ, FOLLOW, AND SAVE ALL SAFETY AND INSTALLATION INSTRUCTIONS
In-ground Installation Instructions
Soil Prep
Fixture Installation Surface Mount
RELEASE DATE
06/26/2023
40429 Brickyard Drive • Madera, CA 93636 • USA
559.438.5800 • FAX 559.438.5900
www.bklighting.com • [email protected]
B-K LIGHTING
REFERENCE NUMBER
INS-2826-00
Conduit
trench
B. Dig hole 15” wide and 12” deep.
Conduit
Trench
Excavated
for Housing
C. Prep soil according to DIG-IT Guide.
A. Determine Soil Type by referencing DIG-IT Guide.
Prep soil according to DIG-IT Guide.
Finished grade
12”
1. Excavate trench according to designed lighting
plan 12” deep and 15” wide suitable for the fixture
housing.
2. Supply primary 120v, branch circuit wiring
necessary for installation.
5. Align holes to final installation orientation. Arrows
on temporary cover point towards screw location
on faceplate for alignment purposes.
NOTE: Do not remove temporary cover until
installation of faceplate.
6. Per DIG-IT Guide, backfill the gap between the
bottom of housing and bottom of hole with sand or
pea gravel for drainage.
NOTE: The mounting collar must be flush
to finished grade. Use stability flange to aid in
installation as shown. Fixture is provided with 5ft
leads.
Stability Flange
Rebar or Stake (Not Included)
Pea Gravel or Sand
Finished Grade
Screws on faceplate will
align with alignment
arrows on temporary
cover
Stability Flange
Rebar or Stake (Not Included)
Pea Gravel
Finished Grade
Pavers
Paver Sand
Soil
7. Fill with soil, then compress. Layer paver sand as
required for paver installation, then install pavers.
Pavers may need to be cut to fit around housing.
3. Slide stability flange onto housing.
NOTE: Product is supplied with a stability flange
to anchor fixture and aid i
n installation
.
4. Loop minimum of 6” wire inside housing to allow
for fixture service. Place fixture in hole.
NOTE:
Do not remove temporary cover!
Standard Installation
DENALI
UPLIGHT - INTEGRAL