Azbil ACTIVAL+ FVY513E Series Скачать руководство пользователя страница 13

AB-7131 

13 

3)  Fully open the valve and flush it out with the maximum flow rate.  

When fluid flows for the first time, it is to clean out the foreign substances and refuse in the pipes.  
The valve is set to fully open when it is shipped from the factory. 

 

 

  CAUTION 

 



After installation, make sure no fluid leaks from the valve-pipe connections. 
Improper piping may cause fluid leakage outside of the valve. 



Do not put a load or weight on this product.  
Doing so may damage the product. 

 

 

Heat insulating 

 

Apply heat insulation as illustrated by 

 in Fig. 6. 

 

If the yoke and/or the actuator are covered with insulation material, the point cannot be checked or may be distorted. 

 

If the heat insulation is inappropriate, accuracy of flow rate measurement and temperature measurement may degrade. 

 

When cutting the insulation material that covers the valve, be sure not to damage the valve sensor cable. 

Heat insulation

Heat insulation

 

Figure 6.  Heat insulating 

 

 

Factory preset position 

The actuator shaft is positioned at 100 % for shipment.  
The shaft is thus completely turned clockwise, and the pointer points at “100.” 

Pointer

 

Figure 7.  Pointer position for shipment 

Содержание ACTIVAL+ FVY513E Series

Страница 1: ...Infilex AC Model WY5117 Flow data stored in Model FVY513EJ FVY514EJ is retrieved via RS 485 communication Modbus protocol The retrieved flow data is effective for energy saving facility operation JIS...

Страница 2: ...Do not freeze this product Doing so may damage the valve body and cause leakage When piping this product be sure there is no foreign matter in the pipes If foreign matter remains in the pipes the prod...

Страница 3: ...control the quality of process fluid water and do not allow rust or foreign object inside the valve Rust or foreign object inside the valve lowers flow rate measuring accuracy Thermally insulate the v...

Страница 4: ...ns of the pipe sensor refer to AB 6923 Specifications Instructions of Temperature Sensor for Pipe Surface Model TY7820Z0P05 Total length 5 m Model TY7820Z0P10 Total length 10 m Model TY7820Z0P30 Total...

Страница 5: ...End connection JIS 20K flanged end raised flange Size Cv Close off rating Model number Nominal size Cv Close off ratings FVY513EJ0012 FVY514EJ0012 DN15 1 2 2 5 1 0 MPa FVY513EJ0013 FVY514EJ0013 DN15...

Страница 6: ...ion 6 pin 3 pin 2 connector Display Panel 4 pin connector Enclosure rating IEC IP54 dust proof and splash proof Operation status indicator LED 1 red LED Status LED indication Normal Repetition of 1 se...

Страница 7: ...FVY513EJ0081 FVY514EJ0081 DN80 3 125 1250 l min Measuring accuracy Factory preset Notes 1 The flow measurement accuracy figures assume a temperature range of 7 17 C or 45 65 C internal pipe pressure...

Страница 8: ...racy and the error due to wiring length 7 Energy calculation accuracy is calculated from the flow rate measuring accuracy at 1 C measuring error of the temperature difference 8 The flow rate measuring...

Страница 9: ...f the product relay terminal block wiring and the relay terminal block load device in connection 2 JCS Japanese Electric Wire and Cable Makes Association 3 KPEV Wire standard provided by Furukawa Elec...

Страница 10: ...water temperature Reset switch Connector for Display Panel 24 V AC Power Port for Display Panel cable Port for temperature sensor Pt100 input cable Port for valve sensor cable Port for temperature se...

Страница 11: ...side of the valve For chilled hot water 40 or more meshes If the strainer cannot be installed just before the inlet of each valve install it on the pipe diverting sections for each piping system Insta...

Страница 12: ...or faces downward Flow direction Flow direction Flow direction Figure 5 Incorrect mounting orientations Piping CAUTION When installing this product hold it in the proper position and securely fasten i...

Страница 13: ...oduct Heat insulating Apply heat insulation as illustrated by in Fig 6 If the yoke and or the actuator are covered with insulation material the point cannot be checked or may be distorted If the heat...

Страница 14: ...ve the actuator may break down Do not manually open or close the valve more than 100 or less than 0 scale 1 Turn off the power 2 Hold the joint using a wrench etc gently turn the wrench to the desired...

Страница 15: ...it may not make proper contact Use crimp terminals with insulation for connections to the product terminals Failure to do so may cause short circuit leading to fire or device failure Tighten the term...

Страница 16: ...sor Pt100 input Terminal Wire color Description Temperature sensor for pipe surface Insertion type pipe temperature sensor T1A Red Red Pt100 A supply water temperature T1B White Black Pt100 B supply w...

Страница 17: ...the recommended cable 1 Pass the 4 core cable of Display Panel through the actuator port for Display Panel See Fig 3 for the location of the port 2 Strip the wire sheath Strip length is 8 mm See Fig...

Страница 18: ...pply cable Attach the optional cable gland with three ports Model DY7000A1000 to the wiring port to share the wiring port with signal lines Connect the wires of RS 485 communication cable to the conne...

Страница 19: ...with multiple 4 20 mA input type products See Figs 23 and 24 4 20 mA control signal input is not isolated from the power and the 4 20 mA input impedance is 282 For connecting a controller the relatio...

Страница 20: ...Terminals 2 6 and 8 of the product are internally connected 3 Refer to 6 Single transformer with two products in the Precautions for connection section Figure 24 Connection example Two Model FVY513EJ...

Страница 21: ...izing pulse output open collector output Model FVY51XEJ This product 3 4 V Protection diode Magnetic counter 0 V Figure 29 Connection example Magnetic counter with relay coil Master Slave Model R seri...

Страница 22: ...y release all the latches start with the one which cannot be visibly checked 1 Press the upper part of one of the male latches 1 in the figure below 2 Press up the lower part of the one of the male la...

Страница 23: ...port 3 Connect the seal connectors optional to the cover of the cable gland IMPORTANT When tightening a seal connector to the cover be sure not to press excessive force on the latches Figure 32 Connec...

Страница 24: ...without insulation sleeve is crimped on a wire end use a tube marker for safety During wire termination do not allow any foreign objects including chips and stripped insulation to get inside the prod...

Страница 25: ...h the base of the cable gland from the wiring port of the product IMPORTANT Carefully handle the O rings attached to the cable gland Check that the cable gland has 3 O rings and be sure to keep these...

Страница 26: ...Visual inspection Semiannual Fluid leakage from the gland and the flange face Loosened bolts Valve and actuator damages Operating status Semiannual Unstable open close operation Abnormal noise and vi...

Страница 27: ...he valve position detecting accuracy Disposal Dispose of this product as industrial waste in accordance with your local regulations Do not reuse all or any part of the product 1 cm Lower setscrew of t...

Страница 28: ...na Fujisawa Kanagawa 251 8522 JAPAN https www azbil com Rev 6 0 Apr 2020 AB 7131 J AI 7131 Rev 4 0 28 ACTIVAL and ACTIVAL are trademarks of Azbil Corporation in Japan or in other countries This produc...