If required, fill in cavity under the baseplate with an equalizing mass.
•
Tighten anchors with a torque wrench.
Each anchor must be able to be tightened to the torque specified by the manufacturer.
Safe operation of the lift is not guaranteed with a lower torque.
•
If an anchor is tightened to the specified torque, then the domed washer lays flat on the
base plate. Secure anchor connection is then guaranteed.
8.1.2 Electrical assembly and power connection
A) with the use of riser and cross-pipes
•
Loosen and remove the upper column cover.
•
Place the cable according to the drawing (Figure 23) into the riser and cross-pipe of the lift
and feed together into the corresponding plug.
•
Pay particular attention for safe contacting of the plug connections.
•
When merging the cable connections at the head plate, ensure that the cable does not
contact rotating parts.
•
The 7-wire motor plug cable (with 2 plugs) is plugged into the head plate on the operating
side, via the riser and cross-pipe and fed to the opposite side and connected to the head
plate of the opposite side.
•
The 3-wire potentiometer cable (with 2 plugs) is also fed via the riser and cross-pipe to the
opposite side and connected with the plug to the head plate of the opposite side.
•
The 5-wire power cable (with one plug) connects the power supply to the head plate of the
operator side.
•
Carefully push the cover panel into the riser pipe from above.