Completion of Work
Before commissioning, check all fastening screws, electrical, pneumatic and hydraulic
lines and, if necessary, tighten these. Warning: in some cases, this must be checked at
regular intervals and tightened if necessary (note in the instructions).
Lift configuration and venting (main lift)
1.
All valves should be closed!
2.
Selector switch on main scissors!
3.
Open connection on the main cylinder (Hose A, Drawing A-2)!
4.
Carefully press the lifting button and watch until hydraulic oil comes out of connection A!
5.
As soon as the air has been released from the line and hydraulic oil appears, close the connection!
6.
Raise the main scissors and leave in end position
7.
Open valve B!
8.
Open bleed valve on main cylinder!
9.
Carefully press the lifting button (if necessary using the additional light barrier muting button)
and watch until oil comes out of the bleed valve on the main cylinder!
10.
As soon as the air has been released from the bleed valve on the main cylinder and hydraulic oil
appears, close the connection!
11.
Carefully press the lifting button until the lift is right at the top. Oil level warning.
12.
Close valve B!
13.
Lower the lift right down!
14.
You can start by equating the guide rails from the main lift via the
balancing valve.
Содержание Cross Lift 50+
Страница 3: ...BEDIENUNGSANLEITUNG ATH Cross Lift 50 ...
Страница 67: ...OPERATING INSTRUCTIONS ATH Cross Lift 50 ...
Страница 131: ...MANUEL D UTILISATION ATH Cross Lift 50 ...
Страница 195: ...NÁVOD K OBSLUZE ATH Cross Lift 50 ...
Страница 259: ...MANUAL DE INSTRUCCIONES ATH Cross Lift 50 ...
Страница 323: ...BEDIENINGSHANDLEIDING ATH Cross Lift 50 ...
Страница 387: ...INSTRUKCJA OBŁSUGI ATH Cross Lift 50 ...
Страница 451: ...NÁVOD NA OBSLUHU ATH Cross Lift 50 ...