4. Now prepare for wiring. Use 4 power cables and 1 PE cable, it is suggested to use a 
5-core  cable(with  PE  included)  for  the  convenience  of  using  the  water-proof  cable 
gland. The live wires shall be at least 16mm², PE shall be greater than 6mm². The PE 
wire shall be crimped to a M6 size ring terminal. Open the 2 locks at the left side of 
the  upper  front  cover  and  open  it.  Connect  the  AC  input  cables  into  the 
corresponding terminals through the cable gland on the bottom left side and fasten 
them(Refer to the Internal view and terminal definition part for wire connection), put 
the transparent cover on the terminal block for safety purpose. Connect the network 
cable through the hole in front of the AC input cable gland to the RJ45 socket and 
fasten the water-proof gland. Turn on the RCBO. Close and lock the upper cover after 
checking internal wiring and breaker position. The wiring is then finished. 

Notice

1. Only  professional  personnel  can  do  the  wiring,  connect  the  AC  input  wires  in 
correct phase order according to the markings on the terminal block.
2. The PE terminal shall be connected to the Earth firmly and reliably!
3. No  live  work!  Turn  off  the  upstream  breaker  in  the  distribution  panel  and  the 
breaker inside the charging equipment before repairing or maintaining.

4. Please do no disassemble the unit unless authorized!

IV. Parameter configuration

After  installed  and  connected,  the  charging  equipment  must  first  be  configured 
according to the actual needs of the user. The parametersare configured through the 
LCD  touch  screen.  Save  the  change  and  exit  then  the  charging  equipment  can  be 
used normally.

After the system enters standby, click thebutton marked by the red rectangle in the 
above figure to enter the system management page, as shown below.

System management page

Mounting pole installation

Содержание EVD-40S

Страница 1: ...ser manual 86 755 2998 8492 T Shenzhen Atess Power Technology Co Ltd 3rd floor building 9 Henglong industrial park the fourth industrial zone of Shuitian community Baoan district Shenzhen China E info...

Страница 2: ...charging equipment is a device that provides high efficiency safe and stable DC power supply for electric vehicles which has a friendly man machine interface and integrates corresponding functions of...

Страница 3: ...stem Parameters 4 2 Network parameters 4 3 Protection parameters V Operation instruction and LCD introduction 5 1 Charging mode and operation 5 2 LCD interface introduction 5 3 Appendix Fault code VI...

Страница 4: ...protection device Note The charging equipment will detect the current status of the lightning arrester module in real time When the lightning protection module is damaged the display will have an ala...

Страница 5: ...nd 3 holes for cable hooker mounting on the wall Take out the expansion bolts in thepacking accessory bag hammer the expansion bolts into the holes Remove the nuts and washers for later use 2 Loosen t...

Страница 6: ...the upper cover after checking internal wiring and breaker position The wiring is then finished Notice 1 Only professional personnel can do the wiring connect the AC input wires in correct phase order...

Страница 7: ...payment is not needed 2 is APP or RFID mode No Parameters Function description 8 9 10 Time set Language set Meter address DC meter s modbus address already preset in factory it is not allowed to modi...

Страница 8: ...Authentication Key OCPP login authentication setting 4 3 Protection parameters The protection related parameters such as voltage current temperature power etc No Parameters Function description 1 2 3...

Страница 9: ...e Charging will start automatically after EV plugged in If you want to stop the charging just press the stop icon on the screen Plug Charge mode operation process flow The charging equipment is equipp...

Страница 10: ...ype in the 4 digit password A wrong password will cause no response and action System parameters page Network parameters page used to set network related parameters of back office server and the charg...

Страница 11: ...Contactor sticking fault AC Input Overvoltage AC Input Undervoltage BMS communication fault VI Specification Model EVD 40S Dimension mm 548 775 294 W H D Weight kg 55KG Display LCD Casing material AC...

Страница 12: ...Over temperature protection Short circuit protection Emergency stop protection Lightning protection Leakage protection 20 50 derate since 50 Ip54 5 95 2000m derate for higher than 2000m Forced air co...

Страница 13: ...etc 4 Failure or damage caused by the installation repair modification or disassembly byunauthorized service personnel 5 Failure or damage caused by using ATESS Power Technology s genuine spare parts...

Отзывы: