1. Remove one scaffold board at a time and stack safely until the stairwell is completely
uncovered.
2. Remove the screws holding the side beams in place.
3. Pull out each side beam one at a time and stack safely.
4. Remove the two screws securing each end of the main beam.
5. Two operatives will need to pull out each end of the main beam and retract it to its
minimum length for its safe removal from the stairwell opening. Carry the main beam down
the stairs and remove from the plot for safe storage.
6. Carry all remaining components downstairs including the scaffold boards and remove
from the plot for safe storage.
Regular inspections of the ASAP platform should be carried out and a record should be
kept. Prior to any insulation a check should be carried out, that all components are not
showing any sign of damage. All damaged or unsuitable components should be replaced
with new parts.
Removal of ASAP