12

Crimped Rib

Uncrimped Rib

Whenever a crimped rib and an uncrimped rib 

meet, the crimped rib should be placed UNDER 

the uncrimped rib if possible. See next page.

Use the diagram to the right when attaching Wall Panels.

           •  Secure the top row to Top Frames

           •  Secure the middle row to Wall Channels

           •  Secure the lower row to Floor Frames

           •  Secure the circled holes to the Panel next to it

FASTEN TO TOP FRAMES

FASTEN TO FLOOR FRAMES

FASTEN TO WALL CHANNELS

7822

IMPORTANT:

  When installing the Wall 

Panels over a Truss, you will need to ‘roll’ 

the Panels as shown to be able to attach the 

next Panel at the overlap. When securing the 

Panel to the building with Small Screws, do 

not insert Screws in the row of holes closest 

to the last rib of the Panel. Next, roll the Panel 

back slightly and attach the next Panel at the 

overlap with a Bolt and Nut in the center hole. 

Once this is done, continue securing the Panel 

to the building.

LEAVE LAST ROW OF HOLES EMPTY

UNTIL NEXT PANEL IS IN PLACE

Step 7 -  Install all Wall Panels.

12J

13

13J

Install ALL Wall Panels:

A)

  Working one side at a time, lift the Panels into place and secure with three Small Screws in the top 

of the Panel, three Small Screws in the middle of the Panel, and  three Small Screws in the bottom 

of the Panel. Roll the Panel back as shown on the previous page and overlap the rib with the rib of 

the next Panel.

B)

  Secure the Panels with a Bolt and Nut thru the center hole at the overlap (see below). Next, fi nish 

securing the Panels to the building with Small Screws as shown in the diagram on the previous 

page. 

C)

  Continue until all Wall Panels have been installed.

Use washers on all fasteners 

used on painted parts.

Place Bolt thru center hole where Panels overlap.

Continue until ALL Wall 

Panels have been installed.

You will need the following parts for this step:

7822  Wall Panel

Содержание GA5M-A

Страница 1: ...rmation Owner s Manual Assembly Guide www arrowsheds com COMMANDER SERIES MOUNTAINEER SERIES Follow all safety precautions in the Commander Mountaineer Series Assembly Manual Two to three people are required for assembly Note It may be helpful to refer to the primary Commander Mountaineer Series Assembly Manual you used when you first assembled your building If you have misplaced your original Comm...

Страница 2: ...s Pliers Carpenter s Level Tape Measure Power Drill Cordless Variable Speed Nut Driver or Wrench Square String for squaring the frame Awl to align holes WHAT YOU NEED RECOMMENDED TIME SAVERS 3 03AQ Check that the following items are included in this carton Reading and following all steps carefully will help make assembly quicker and easier Before you begin assembly be sure to confi rm that all the ...

Страница 3: ...ners included in this Module when reinstalling parts 146 1 cm 146 1 cm 10881 10882 10881 10882 10881 10882 Hex Nut 11 32 Hex SB 2 Phillips SS 2 Phillips LS 2 Phillips The following fasteners are used throughout assembly Be sure to use the proper fastener where indicated Square Nut 10 32 LB 2 Phillips 5 05AQ Next insert the Upper Lower Chord Truss Assembly into the Truss Post Assembly as shown Secu...

Страница 4: ...ent Panels in order to remove the Panels shown Place these parts in a safe place until they are needed later A C Remove Screw at bottom of End Roof Panels before continuing Remove four Bolts at end of Ridge Cap Remove Roof Trim D Remove last two Bolts 6 06J Partially disassemble the rear of the building A Remove the rear Roof Trim from both sides of building B Remove four Bolts from rear Ridge Cap...

Страница 5: ...C A Step 4 Remove the Rear Wall 9 09AQ Step 5 Install all new Truss Sections A Attach the Side Frame that came with the Module to the rear of the building as shown with two Bolts and Nuts Side Frames should overlap by 8 1 4 21 0 cm Attach the Truss Assembly to the Floor Frame 57 1 2 146 1 cm behind the previous Truss using a Large Screw You will need the following parts for this step 10625 Side Wa...

Страница 6: ... cm B C D Step 5 Continued 10650 10650 10650 10650 10887 10625 10625 Overlap Length 11 11J Step 6 Reinstall the Rear Wall Once all Truss Sections have been erected you may reinstall the Rear Wall as follows A Fasten the Rear Wall to the Floor Frame with Large Screws B Fasten the rear Wall Channels from the last Truss with Large Screws C Fasten the Side Wall Angle to the Rear Wall with Large Screws...

Страница 7: ...lap with a Bolt and Nut in the center hole Once this is done continue securing the Panel to the building LEAVE LAST ROW OF HOLES EMPTY UNTIL NEXT PANEL IS IN PLACE Step 7 Install all Wall Panels 12J 13 13J Install ALL Wall Panels A Working one side at a time lift the Panels into place and secure with three Small Screws in the top of the Panel three Small Screws in the middle of the Panel and three...

Страница 8: ... Extension Module you are installing and set aside for later use 4 6 8 10 12 15 Working with one Truss Section at a time A Attach one end of the Mid Ridge Cap to the Front Ridge Cap with two Bolts and Nuts B Install four Roof Panels C Seal the ridge of the building with Weather Stripping D Where Panels overlap under the Ridge Cap secure with Bolts and Nuts and seal with a strip of tape see page 14...

Страница 9: ...d anchor the added sections of the building in the same manner as the rest of the building J I With two Panels remaining E Attach the end of the rear Ridge Cap with two holes to the Mid Ridge Cap with two Bolts and Nuts F Install the last two Roof Panels G Seal the ridge of the building with Weather Stripping H Where Panels overlap under the Ridge Cap secure with Bolts and Nuts and seal with a str...