Insulating with Arma-Chek D >> Using Pre-Covered Sheets

© ARMACELL UK LTD.

 

D

  APPLICATION MANUAL

3 - Insulating with Arma-Chek D >> Using Pre-Covered Sheets

FLANGE COVERINGS

Fabricate fl ange coverings following the same principles 
as for valve coverings.

FLAT SURFACES

Flat  surfaces  are  always  completely  covered  with  ad-
hesive; on the Armafl ex and metal substrate surfaces. 
Cylindrical bodies with an outer diameter of ≥ 600 mm ( 
≥ 500 mm for off-shore applications) are treated as fl at 
surfaces.
1.  Around the butt joint, leave 30 mm at the edge of the 
   sheet  of  factory-coated  Arma-Chek  D  free  of  ad-
   hesive  and  place  the  sheet  in  position  with  5  mm 
   overlap.

   
2.  Press  the  overlapping  edge  of  the  sheet  into 
   position.

   
3.  Wet seal the butt seam.

   

Schedule for glueing insulation to fl at surfaces

DUCTWORK RECTANGULAR 

1.  Insulate  the  area  of  the  ductwork  which  borders 
   directly  on  the  fl ange  with  a  100  mm  wide  strip  of 
   Armafl ex.
   Determine the dimensions of the ductwork surface to 
   be insulated. On bends the inner (throat) and outer 
   dimensions  are  determined  using  strips  of  factory-
   coated Arma-Chek D.

2.  Cut and apply Arma-Chek D precoated sheets, use 
   adhesive allover as described in chapter ”Insulating 
   fl at surfaces“.

3.  Use factory-applied precoated Arma-Chek D tubes to 
   insulate  fl anges  (rule  of  thumb:  half  of  tube  inner 
   diameter e fl ange overlap).
   Install  these  tubes  following  the  description  in 
   ”Fabrication of bends with Arma-Chek tubes“ point 2 
   and 3 (see page xx).
   Cut the tube in half and dimension according to the 
   length  of  the  fl ange  (use  45°  mitred  cut  for  the 
   corners  of  the  fl ange).  Install  the  halved  tubes.  Be 
   sure to bond carefully!

 

1/2 pre-coated 

 

Arma-Chk D tube

4.  Cover  uncoated  Armafl ex  strips  around  the  fl ange 
   with Arma-Chek D self- adhesive tape or strips.

Arma-Chek D 

pre-coated sheet

N

ote:

a.  All  butt  joints  must  be  secured  with  50  mm  wide 
   selfadhesive Arma-Chek D tape. Secure edges with 

(12) D

Содержание Arma-Chek D

Страница 1: ...application manual ARMA CHEK D application manual application manual ARMA CHEK D D...

Страница 2: ...application manual ARMA CHEK D ARMACELL UK LTD D APPLICATION MANUAL D...

Страница 3: ...ways use the correct speci ed Arma ex adhesives Do not assume they will always do the same job If in doubt consult the Armacell technical department local agent On external installations always ensure...

Страница 4: ...ntire surface smoothing the covering round making sure there are no air pockets present Always check for alignment and avoid creases and crinkles during that time e If the surfaces are left to dry too...

Страница 5: ...clean the seams and joints use the Arma ex cleaner Peel back release paper and cover the entire seam line with an additional 50 mm overlap where appli cable applying pressure during the installation C...

Страница 6: ...General Working with Arma Chek D ARMACELL UK LTD D APPLICATION MANUAL 1 General Working with Arma Chek D 4 D...

Страница 7: ...d x using the factory applied adhesive strip 5 Use correct Arma ex adhesive to secure the longi tudinal seam Apply on one side only Always remember to stagger longitudinal seams 6 Secure the butt end...

Страница 8: ...seam of the throat using 20 mm wide Arma Chek S Butyl Tape Always ensure the tape is applied such that a watershed is achieved Note In some circumstances it may be preferable to fabricate segment ttin...

Страница 9: ...ARMAFLEX TUBE Note Yellow lines indicate where cuts are to be made Always follow instructions related to the application of pre coated Arma Chek S tubes as stated in the above procedures relating to a...

Страница 10: ...over the tting The oversize tting should extend by the wall thickness of the over sized fabrication minimum of 25 mm is required over the adjoining insulation On the butt end of the adjoining insulat...

Страница 11: ...ness 1 mm 1 This table is valid for ambient conditions of 5 C For lower applica tion temperatures the rigidity and tension of the sheet material can increase thus lead ing to other conditions than men...

Страница 12: ...e by drawing the half elevation on the edge of the Arma Chek sheet 4 Completed Arma Chek pipe reducer made of factory coated Arma Chek Dsheet material with a straight nish ECCENTRIC REDUCER FLAT BACK...

Страница 13: ...meter of the connected pipes 2 x ins thickness Note 5 mm must be added to the jacket height deter mined 5 mm must be subtracted from all measur ments for openings 2 Cross section A A Determine the cir...

Страница 14: ...borders directly on the ange with a 100 mm wide strip of Arma ex Determine the dimensions of the ductwork surface to be insulated On bends the inner throat and outer dimensions are determined using st...

Страница 15: ...HANGING DUCTWORK Use the Arma x duct supports to optimize the preven tion of thermal bridging and simplify the hanging of duct work VESSELS 1 First insulate the vessel jacket with Arma Chek D pre coat...

Страница 16: ...Insulating with Arma Chek D Using Pre Covered Sheets ARMACELL UK LTD D APPLICATION MANUAL 3 Insulating with Arma Chek D Using Pre Covered Sheets 14 D...

Страница 17: ...are no gaps present in all the seams and joints Note Refer to the Arma ex Installation Manual at all times 2 For Arma Chek D covering adhesive is only required on the Arma ex and on the overlapping ar...

Страница 18: ...ongitudinal seam of the covering with the correct Arma ex adhesive Continue to install the covering along the ductwork allowing for a 50 mm overlap on all butt joints DUCTWORK BENDS IRREGULAR SHAPES 1...

Страница 19: ...seg ment of the assembled segment bend and determine the circumference 2 Transfer the circumference measurement U to the Arma Chek Dcovering material and draw in a line dividing it in half Now add a 5...

Страница 20: ...pipe and transfer this to the covering material Halve the circumference 3 Transfer segment width for the throat seam to each end of the circumference drawn and the segment width for the back of the be...

Страница 21: ...a pair of scissors OFFSET ANGLES 1 Determine the circumference U of the Arma ex in sulated offset angle the maximum a and minimum b height and the Arma ex insulated outer diameter of the pipe D to wh...

Страница 22: ...material to the insulation material Secure the seams with Arma Chek D self adhesive tape on indoor applications with 100 mm wide strips of the covering material applied with all over adhesive coverag...

Страница 23: ...eathering overlap length minimum equal to the insulation thickness of the non covered area Method 2 1 Measure the following diameters of the end cap a smaller insulated outer diameter of insulated bod...

Страница 24: ...ARMACELL UK LTD D APPLICATION MANUAL 4 Covering Using Arma Chek D Covering Covering Of Insulated Objects Using Arma Chek D Covering 22 D...

Страница 25: ...application manual ARMA CHEK D ARMACELL UK LTD APPLICATION MANUAL D D...

Страница 26: ...ightweight and easy to apply insulation system resistant to mechanical impact D D Arma Chek R The insulation system with extra system security that minimises the risk of under insulation corrosion UIC...

Отзывы: