APstorage Installation / User Manual
23
3. Installation
3.10 Start-up Sequence
3.10.1 Power ON
Once the unit has been properly installed and the batteries are connected well, turn on the
batteries, then turn on the Battery Breaker, Grid Breaker, Backup Breaker and Main breaker to
power the system.
3.10.2 Check the System
Please refer the chapter 4.5.1 to check the system.
WARNING:
Installation must be performed with care.
Before making the final DC connection or closing DC breaker/disconnect,
be sure po) must be connect to po) and negative( -) must be
connected to negative(-). Reverse polarity connection on battery will
damage the inverter.