Installation (Vent-Air Intake System Installation) continued-
Figure 10
8. Extend the five (5) inch
(12.7 cm)
diameter telescopic tube to its
maximum length. Place the large end of the five (5) inch
(12.7 cm)
diameter telescopic tube over the collar on the outer wall mount plate.
Drill three (3) 1/8 inch diameter holes, 120
o
apart, through the five (5)
inch
(12.7 cm)
diameter telescopic tube into the collar on the outer wall
mount plate. Fasten with three
(3) #8 sheet metal screws (supplied).
Using the supplied special RTV silicone sealant, apply a sufficient
amount to seal the joint (See Figure 11).
Figure 11
Содержание DIRECT VENT GAS WATER HEATER
Страница 10: ...10 Installation continued Figure 2 Figure 3 ...
Страница 15: ...15 Installation Horizontal and Vertical Vent Air Intake Lengths continued Figure 6 ...
Страница 27: ...27 Water Connections continued ...
Страница 37: ...37 DIRECT VENT WATER HEATER ...
Страница 38: ...38 VENT AIR INTAKE KITS ...
Страница 40: ...40 NOTES ...