E. EXHAUST REQUIREMENTS
1. General Exhaust Duct Work Information
Exhaust duct work
should be
designed and installed by a qualified professional. Improperly sized duct
work will create excessive back pressure which results in slow drying, increased use of energy, overheating
of the dryer, and shutdown of the burner by the airflow (sail) switches, burner hi-limits, or basket (tumbler)
hi-heat thermostats.
CAUTION
: DRYER
MUST BE
EXHAUSTED TO THE OUTDOORS.
CAUTION: IMPROPERLY
SIZED
OR
INSTALLED
EXHAUST
DUCT
WORK
CAN
CREATE
A
POTENTIAL
FIRE
HAZARD.
The duct work
should be
laid out in such a way that the duct work travels as directly as possible to the out-
doors with as few turns as possible. Single or independent dryer venting is recommended.
Horizontal Venting:
When single drying venting is used the length of duct work from the dryer to the outside exhaust outlet
should not
exceed fifteen (15) feet. The minimum diameter of this duct work
must be
at least 10-inches.
In the case of multiple (common) dryer venting, the distance from the last dryer to the outside exhaust outlet
should not
exceed (15) feet. The shape of the duct work is not critical so long as the minimum cross-
sectional area is provided. It is suggested that the use of 90° turns be avoided; use 30° and/or 45° angles
instead. The radius of the elbows
should preferably be
1-1/2 times the diameter of the duct. Including
basket (tumbler)/dryer elbow connections or elbows used for outside protection from the weather, no more
than two (2) elbows
should be
used in the exhaust duct run. If more than two (2) elbows are used, the
cross-sectional area of the duct work
must be
increased.
ALL
duct work
should be
smooth inside with no
projections from sheet metal screws or other obstructions which will collect lint. When adding ducts, the duct
to be added should overlap the duct to which it is to be connected.
ALL
duct work joints
must be
taped to
prevent moisture and lint from escaping into the building. Inspection door
should be
installed at strategic
points in the exhaust duct work for periodic inspection and clean-out of lint from the duct work.
Vertical Venting:
When single dryer venting is used the length of the duct work from the dryer to the outside exhaust outlet
should not
exceed twenty (20) feet. The minimum diameter of this duct work
must be
at least 12- inches.
In the case of multiple (common) dryer venting, the distance from the last dryer to the outside exhaust outlet
should not
exceed twenty (20) feet. The shape of the duct work is not so critical so long as the minimum
cross sectional area is provided. It is suggested that the use of 90º turns be avoided; use 30º and/or 45º bends
instead. The radius of the elbows
should preferably be
1-1/2 times the diameter of the duct.
ALL
duct
work
should be
smooth inside with no projections from sheet metal screws or other obstructions which will
collect lint. When adding ducts, the duct to be added should overlap the duct to which it is to be connected.
ALL
duct work joints
must be
taped to prevent moisture and lint from escaping into the building. Inspection
door
should be
installed at strategic points in the exhaust duct work for periodic inspection and clean-out of
lint from the duct work.
IMPORTANT
: Exhaust back pressure measured by a manometer in the exhaust duct
should not
exceed 0.3 inches of water column.