This shower system is designed to be installed on a level, bare floor. It is necessary for any existing shower to be 

completely removed. Tear out and remove all old material to expose the 2 x 4 wall studs. Clean up the shower 

area, removing all dust and old material from the area.

Cold Weather Warning

: We recommend not installing your shower below the temperature of 70°F.  The shower will 

be fine in cold weather after installation, but during installation bending and handling shower components in 

cold weather can cause breakage. Frigid conditions can make some shower components brittle and susceptible 

to cracking during rough installation handling.

2

DRY-FITTING THE PAN

TIME

½ to 1 HR

½" cement 

board 

2 x 4 stud

metal flange

diagram 1

floor of pan

silicone bead

It is easier to check alignment of studs and pan without the drain 

installed into the pan. 

Place the pan in the planned position. Check to see that the 

spacing between the metal pan flange and 2 x 4 studs are flush. 

Some shimming or sanding of the 2 x 4 studs may be required to 

flush the studs with the metal pan flange. When screwing in the 

½" cement board the metal flange will pull fast to the studs, and 

will secure the pan in place. (

dia. 1

)

PRE-INSTALLATION TEAR DOWN

TIME

8-16 HRS

1

INSIDE

NOTE: Due to some rough handling during shipping, water 

test pan before installation to check for any issues.

PRE-INSTALLATION TEAR DOWN

TIME

8-16 HRS

1

OPTIONAL SHAMPOO SHELF INSTALLATION

TIME

1/2 - 1 HR

4. On the 2 tiles the Shampoo Shelf will be replacing,

mark 1" from the outside of the grout line, the cut-out

area will be 10" x 22". Cut out the hole for the Shelf.

The smaller the hole the better.

5. Dry-fit the Shampoo Shelf for alignment of grout lines.

6. Using 100% Silicone in-place with a generous  b ead

around the back of the lip, wipe off excess silicone

with tissue.

1. The Shampoo Shelf was designed to match your tile

size 12" x 24" tiles, the cut-out hole size is 10" x 22".

2. There is a 1" lip or frame around the Shampoo Shelf,

this will be the water sealed area for the Shampoo

Shelf.

3. The best way to cut the hole is with a small 5" round

diamond blade.                                                          

See detailed instructions enclosed with Shampoo Shelf

IMPORTANT: DO NOT USE SHIMS UNDER THE SHOWER PAN. SHOWER PAN MUST SIT ON A FLAT LEVEL FLOOR.

SILICONE

Each shower will typically require between 12-24 tubes depending on your size and configuration. There are different 

brands that make RTV silicone (e.g. "DAP", "LOCTITE", or "A.S.I.") or we also recommend the use of GE Silicone II. You 

can purchase silicone on our website under Shower Accessories.

Содержание Medici showers NEO ANGLE

Страница 1: ...re a licensed contractor handyman or professional installer that can do it for you Installation time may vary depending on your experience complexity of shower and Pre Install Prep Work which may incl...

Страница 2: ...secure the pan in place dia 1 PRE INSTALLATION TEAR DOWN TIME 8 16 HRS 1 INSIDE NOTE Due to some rough handling during shipping water test pan before installation to check for any issues PRE INSTALLAT...

Страница 3: ...f triple studs overhang 11 minimum gap required for shampoo shelf diagram 2 1 Locate the drain assembly to install into pan 2 3 4 Take drain assembly apart and set parts 1 4 in a safe place for instal...

Страница 4: ...prior to the cement board To do this staple plastic so that it hangs 1 above the floor DO NOT USE AN ELASTOMERIC WATERPROOFING MEMBRANE ON YOUR CEMENT BOARD such as RedGard Roofing nails may be used...

Страница 5: ...Place the first side casing into position making sure to align with the vertical plumb line previously drawn on the cement board Apply pressure to the side casing to bond it to the cement board The s...

Страница 6: ...ws and blocks or another person place the upper panels 4 3 into position Check the length and overlap alignment Some fitting may be required Depending on your faucet selection you may need to mark and...

Страница 7: ...existing walls or panels Sistine Stone wall panels are made to be flexible and may have a slight bow This condition is normal and wall panels will flatten out when properly installed If wall panels h...

Страница 8: ...and straight to each other Measure diagonally to check for straightness Make any necessary adjustments dia 21a 3 Locate the header pieces and lay them out in the correct orientation on the shower pan...

Страница 9: ...stallation with the hinges on the right side 1 Have one person place the door in its open position by allowing the bottom hinge pin to slide into the threshold hinge bracket Make sure the bottom hinge...

Страница 10: ...glass panels are in the proper position 5 Allow the silicone to dry You can silicone any gaps between the stone and glass to ensure water tightness G Install Glass Door Header 1 2 3 Have someone help...

Страница 11: ...t holes Insert the anchor through pilot holes apply silicone to back edge of shelf and then screw shelf to wall 4 You can install the soap dish with silicone a Silicone Installation Apply silicone to...

Страница 12: ...over the cracked seam when it is installed The grout will correct the problem you will not be able to tell the crack was ever there Scratches Blemishes Can be removed by wet sanding the tile surface...