8.  User & Operating Instructions. 

8.1 

To Start the Heater 

 

1. Ensure gas supply is turned on. 
 
2. Electrical supply to the controls is on. 
 
3. Ensure that the controls are correctly set 

i.e.; 

 



Clock is correctly set. 



Heater program is correctly set. 



Required room temp is correctly set 

 
4. Once the heating controller ‘calls for heat’ 

power will be supplied to the heater(s). The 
red power on  neon will then illuminate. 

 
5. After a pre-purge period of 10 seconds the 

burner will ignite and the amber low fire 
neon  will  then  illuminate.  If  the  heat       
demand is not achieved on low fire, then 
the amber high fire neon will illuminate. 

 
6. If lockout occurs press the lockout reset 

button (if available), or switch off electrical 
supply and restart after 15 seconds. 

 
7. If lockout occurs three times consecutively 

switch  off  and  isolate  the  gas  and         
electricity supplies. 
Contact the AmbiRad Service department.

 

 
 
 
8.2.  To Switch Off Heater 
 

1. Switch off electrical supply to the heater. 

The burner will stop and the fan will shut 
off. 
 

2. If the heater is to be switched off for      

periods in excess of one week it is highly    

recommended that both the gas and the 
electrical supplies are turned off. 
 

8.3.  Routine Maintenance between Service 

Intervals 

 

After ensuring that the heater is cold and 
mains  electricity  isolated,  cleaning  of  the        
reflectors  with  a  soft  cloth  and  a  mild          
detergent (non solvent based cleaners only) 
in water can be undertaken. 

 

Additional removal of dust from the radiant 
tubes and burner  can be undertaken. 
 
 
 

8.4   Frequency of Servicing 
 

The manufacturer recommends that to 

 

 

ensure  continued  efficient  and  safe         
operation of the appliance, the heater is 
serviced annually by a competent person, 
e.g.  every  year  in  normal  working           
conditions, but in exceptionally dusty or  
polluted conditions more frequent servicing 
may be required. 

 
 

The manufacturer offers a maintenance     
service. Details are available on request. 

 
 

For Service requirements, please contact   
AmbiRad. 

 
 

For further technical and service support 
visit our Support Information Database at     
www.s-i-d.co.uk 

Nortek Global HVAC is a registered trademark of Nortek Global HVAC Limited. Because of continuous product innovation, Nortek Global HVAC reserves the right to change product specification without due notice. 

 

NORTEK GLOBAL HVAC (UK) LTD 

Fens Pool Avenue 

Brierley Hill 

West Midlands  DY5 1QA 

United Kingdom 

 

Tel: 

01384 489 250

 

Fax: 

01384 489 707

 

 

[email protected] 

www.ambirad.co.uk 

Registered in England No. 1390934. Registered office: 10 Norwich Street, London, EC4A 1BD 

Содержание VISION VT Series

Страница 1: ...Pool Avenue Brierley Hill West Midlands DY5 1QA WARNINGS Nortek Global HVAC UK Ltd equipment must be installed and maintained in accordance with the relevant provisions of the Gas Safety Installations...

Страница 2: ...4 10 Re commissioning after Service 5 Spare Parts 6 Fault Finding Guide 7 Replacing Parts 7 1 Burner Controller Replacement 7 2 Air Pressure Switch Replacement 7 3 Gas Valve Replacement 8 User and Op...

Страница 3: ...heater support lugs should be made by a speed link D shackle or in the case of drop rods a closed formed hook The hanging attachments to over head steelwork etc must be purpose made to good sound eng...

Страница 4: ...Pin must be tightened by pliers Drop rod with formed hook note hook or eyebolt must be closed tight 15 max ON U TUBE VARIANTS THE HEATER SHOULD SLOPE DOWNWARDS TOWARDS THE RETURN BEND AND ON LINEAR V...

Страница 5: ...e tables below These minimum distances MUST be adhered to at all times Figure 2 a Diagram illustrating the clearance to combustibles VTUT VTAUT VTCUT 25 Above Reflector A 180 Above Burner Heater Outle...

Страница 6: ...Above Burner B 500 To the Sides C 750 Below Tubes D 1700 Horizontally from Heater Outlet UNFLUED E 1200 End Wall F 500 Above Heater Outlet FLUED G 150 Above Heater Outlet UNFLUED G1 500 Figure 2 b Di...

Страница 7: ...on in between these angles is acceptable A clearance distance x of min 200mm must be observed to allow side door access Care must be taken to observe the minimum pipe bend diameter minimum 250mm maxim...

Страница 8: ...Live Black Live It is recommended the heater or group of heaters are controlled by thermostats a time switch and if required manual control switches and a frost thermostat We recommend use of AmbiRad...

Страница 9: ...9 2 1 Pressure Switch Power ON red BR BL R GR Y GR N L 230V AC SUPPLY F1 N F2 HIGH FIRE TERMINAL 21 14 24 11 A2 12 22 A1 High Fire Relay COIL NC 230V AC FAN TERMINALS 2 1 N L H N L BK 3 EMC FILTER Lo...

Страница 10: ...Mulitizone NEUT LIVE HEAT 2 OUTPUT HEAT 1 OUTPUT LIVE NEUTRAL IMPORTANT Add this link wire 1 L 2 N 10 S R0S R1D0 D1 41 40 7 8 9 25 14 5 6 NOTES BLACK BULB SENSOR may be placed at a max distance of 10...

Страница 11: ...1 41 40 7 8 9 25 14 5 6 NOTES BLACK BULB SENSOR may be placed at a max distance of 100m from the control unit using screened 0 75mm cable Wiring should be kept separate from mains wiring to minimise n...

Страница 12: ...W free area 1 8 2 Flued Radiant Heater In buildings having an air change rate of less than 0 5 per hour additional mechanical or natural ventilation is required For detailed information please see BS6...

Страница 13: ...hould be adequately supported from the building structure and installed in accordance with the British Standard Code of Practice BS 5440 Part 1 Installation and maintenance of flues and ventilation fo...

Страница 14: ...flued x500 60 VT A C 25LI8 390x7867 unflued x315 53 VT A C 25LI10 5 390x10467 unflued x315 72 Table 4 Natural Gas G20 Heat Input kW Gas Flowrate l hr Injector Pressure mbar Injector Size mm Gross Nett...

Страница 15: ...bends 2 Maximum flue run 9 5m 125mm Maximum no of bends 2 All flues must terminate vertically For further information on flue runs please refer to section 1 10 1 and BS 5440 pt 1 A 127mm 5ins Twin Wa...

Страница 16: ...plied using grub screw provided Figure 7b E A Standard end terminal unflued 201866 SUB B Tube to Flue Coupler 75mm 201813 C Flue Bend 202662 D Two Stage Burner A 127mm 5ins Twin Wall Flue System B Tub...

Страница 17: ...ng the correct length and quantity are inserted into their respective correctly identified tube as detailed in the assembly drawings PLEASE READ this section prior to assembly to familiarise yourself...

Страница 18: ...or joining radiant tubes locate and position tube couplers at the end of the tube so that the socket heads are facing outwards Tighten clamping bolt arrangement to secure ensuring the bolts are not ov...

Страница 19: ...dvice note before identifying the correct model drawing 2 2 8 Burner Assembly On VTUT only slide the burner assembly onto the RIGHT HAND TUBE when viewed from above ensuring it is fully engaged Secure...

Страница 20: ...Doc No 700025 Page 20 of 32 Figure 7 Vision Heater Assembly Models VTUT VTAUT VTCUT U tube 25kW FIGURE 1 FIGURE 1 M6 FIGURE 2 FIGURE 3 SEE FIGURE 1 SEE FIGURE 2 VT25UT 5180 25 35 1935 2293 225...

Страница 21: ...32 Figure 8 Vision Heater Assembly Models VTLF VTALF VTCLF 25kW 8m 75mm 3ins Nom Dia IMPORTANT ENSURE FIRST REFLECTOR OVERLAPS SECOND REFLECTOR SECOND REFLECTOR OVERLAPS THIRD FIGURE 1 FIGURE 2 V T 2...

Страница 22: ...gure 9 Vision Heater Assembly Models VTLF VTALF VTCLF 25kW 10 5m 75mm 3ins Nom Dia IMPORTANT ENSURE FIRST REFLECTOR OVERLAPS SECOND REFLECTOR SECOND REFLECTOR OVERLAPS THIRD FIGURE 1 FIGURE 2 V T 2 5...

Страница 23: ...rner on tube and secure Open control housing and check that all components are securely fastened Reconnect gas hose Open isolating valve Check soundness A successful ignition is indicated by the amber...

Страница 24: ...er 4 1 Tools Required The following tools and equipment are advisable to complete the tasks laid out in this manual Suitable alternative tools may be used Large Adjustable Spanners or 22 26 27mm Spann...

Страница 25: ...the burner bracket Slacken the set screws on the burner support casting to enable the burner to be removed from the radiant tube Step 6 Remove the burner and position the burner in a safe area to pre...

Страница 26: ...any dust with a soft brush Step 6 Remove any dust from fan scroll and from around the motor Step 7 Ensure the impeller rotates freely Step 8 Refit components 4 6 Burner Head and Electrode Servicing S...

Страница 27: ...7 Refit components Step 4 Withdraw the turbulators from the appliance Carefully noting their condition and position Replace turbulators if necessary Step 5 The turbulators should be cleaned with a so...

Страница 28: ...ropane Item 201284 Ignitor Assembly Part No Description 200988 Pepperpot Head Item 2175 Amber Neon Hi and Lo fire 2180 Red Neon Power On 200420 Jet Carrier 202490 Combustion Fan 201488 2 Gasket Set 90...

Страница 29: ...the vacuum switch pull in Check 1 Wiring harness plugs 2 Vacuum switch operation 3 Replace fan Is the burner sparking Does the gas valve open Check 1 Burner controller 2 Replace gas valve Check 1 Vac...

Страница 30: ...e HT Lead from burner controller Step 4 Disconnect burner controller from the wiring harness Step 5 Fit new burner controller Step 6 Refit HT leads and refit burner controller to wiring harness Step 7...

Страница 31: ...Step 3 The burner head can now be detached by disconnecting the impulse tube and the burner head wiring Step 4 Detach the four screws securing the front of the gas valve Step 5 Remove the four screws...

Страница 32: ...and the electrical supplies are turned off 8 3 Routine Maintenance between Service Intervals After ensuring that the heater is cold and mains electricity isolated cleaning of the reflectors with a sof...

Отзывы: