Installation Instructions
It is assumed that the Pre-Installation Checklist steps are complete.
NOTE
Base Installation
1. Align the base plate over the conduit opening and
mark the location of each anchor hole. Remove the
base plate when finished.
2. Using a hammer drill and 5/8" concrete drill bit, drill
four (4) anchor holes to a depth of 3" (64mm)
[Figure 8].
3. Using a shop vac, vacuum any debris from the
anchor holes. Anchors will not tighten properly if
debris is present.
4. Insert anchors threaded side down [Figure 9].
5.
Ensure each anchor is flush with the surface of the
concrete. If necessary, use a hammer to tap the
anchors until they are flush.
The barrier home position will align with an anchor
hole [Figure 7].
NOTE
Drill Anchor Holes
Figure 8
Insert Anchors
Figure 9
Base Plate / Barrier Alignment
Figure 7
Barrier Home
Position
Anchor
Hole
Conduit
Hole