BUILDING EDGE PROTECTION SYSTEM   Instruction for use

To 

disassemble the posts you

 should start from disassembling the intermediate railing by bouncing the end rods with 

the hammer. Then you should disassemble the toeboards. The main railing should be disassembled last before the 
posts are disassembled. To disassemble the posts remove to M12 screws. In general, the disassembly is opposite to 
the assembly.

•  The system transfers static loads only, do not use it when the dynamical loads are present.
•  The system may be used when the wind speed does not exceed 30 m/s.
•  When the building edge is covered with ice and the working surface is slippery remove the ice and the reason why 

the surface is slippery before the protection system is installed.

•  When the building edge is covered with snow remove it before the system in installed.

Should people or objects be caught (fall) in emergency you should inspect the components.

Railings:

• railings with the bent or torn section should be scraped,
• railings bent by no more than 10 cm from the straight line can be repaired by straightening,
• railings with the damaged red shrink jackets should be repaired by installing new jackets.

Posts:

 

• posts with the bent section should be scraped,
• posts with the torn section should be scraped,
• posts with the pipe section permanently bent by more than 5 cm from the straight line should be scraped,
• posts with the broken mounting rods should be repaired by re-welding and re-painting,
• posts with the broken end rods should be scraped,
• posts with the bent fastening rods should be straightened,
• posts with the bent foot plates should be repaired by straightening,
• posts with the cracked welds should be repaired,
• posts with the bent, twisted toeboard handles should be straightened.

Toeboards:

• toeboards with the crosswise cracks should be scraped,
• toeboards with the longitudinal cracks exceeding 200 mm should be scraped,
• toeboards with the falling knots should be scraped.

Should people or objects be caught (fall) in emergency a competent person should check (inspect) 
the components and the protection system.

SYSTEM USAGE

HANDLING OF DAMAGED COMPONENTS

4

5

4   SYSTEM USAGE     /     5   HANDLING OF DAMAGED COMPONENTS

Содержание MOSTOSTAL E823800

Страница 1: ...INSTRUCTION FOR USE TEMPORARY BUILDING EDGE PROTECTION SYSTEM MOSTOSTAL SCAFFOLDING FORMWORK OVER 20 YEARS OF ALTRAD MOSTOSTAL STRENGTH MODERNITY STABILITY...

Страница 2: ...I N S T R U C T I O N F O R U S E altrad mostostal pl altradmostostal TEMPORARY BUILDING EDGE PROTECTION SYSTEM MOSTOSTAL SCAFFOLDING FORMWORK...

Страница 3: ......

Страница 4: ...Instruction for use TABLE OF CONTENTS 1 GENERAL 2 DESCRIPTION OF COMPONENTS 3 QUICK ASSEMBLY AND DISASSEMBLY GUIDE 4 SYSTEM USAGE 5 HANDLING OF DAMAGED COMPONENTS 6 COMPONENT STORAGE AND PACKING 7 LI...

Страница 5: ...e than 15 the use of the system shown in the instructions is prohibited The temporary safety protection system belongs to the general protection systems which are required and used during the construc...

Страница 6: ...g The pipe toler ance is compliant with PN EN10219 The railing pipes are galva nized and finished with red shrink jackets over 200 mm They indicate the railing zone that should protrude beyond the pos...

Страница 7: ...eces are missing that are the integral part of the railings or the pipe sections are not bent and make the components malfunc tion The pipes 33 7 x 2 6 which are used as the main and intermediate rail...

Страница 8: ...sleeve into the hole position the post and screw it to the surface with a torque of 50 Nm The arrow on the label on the post foot indicates the proper post position in relation to the ceiling edge fi...

Страница 9: ...cking them by hitting the end rod with the 600 g hammer from above The railing pipes must always be located on the in side of the building The railing pipes should protrude beyond the supporting point...

Страница 10: ...ailings bent by no more than 10 cm from the straight line can be repaired by straightening railings with the damaged red shrink jackets should be repaired by installing new jackets Posts posts with th...

Страница 11: ...g not applicable to the packs used on the construction site and in the customer warehouse storage tag 825 1200 3000 900 steel galvanized strap DX51 Z275 MAC 32 x 0 75 mm steel galvanized strap DX51 Z2...

Страница 12: ...M Instruction for use Component name Contr no Weight kg Picture Versatile post ZZA023 7 69 Post railing ZZA024 6 1 Modular palette E823800 40 2 Storage palette ZZA022 42 5 Toeboard L 3 0 m H 0 15 m S...

Страница 13: ...12 BUILDING EDGE PROTECTION SYSTEM Instruction for use NOTES...

Страница 14: ...019 ALTRAD MOSTOSTAL Sp ka z o o ul Starzy skiego 1 08 110 Siedlce Poland Tel 48 25 644 72 84 Fax 48 25 633 32 78 Email handlowy altrad mostostal pl www altrad mostostal pl MOSTOSTAL SCAFFOLDING FORMW...

Отзывы: