18
Subject to technical amendments without notice | 83050700gUK – Translation of the original operating manual | ait-deutschland GmbH
Bleeding the unit
The unit is bled automatically if the bleeder (vent valve)
of the safety assembly is open. If the heating circuit is
filled or drained, the venting valve of the safety assem
-
bly opens.
Bleeding the circulation pump of the heating
circuit
Unscrew the screw cover in the middle of the circula-
tion pump until loose and close again after venting.
Bleeding the domestic hot water tank
To bleed the domestic hot water tank, the domestic hot
water charge circuit must be flushed separately.
To do this, manually switch the domestic hot water
changeover valve to domestic hot water charging.
After bleeding, return it to the initial position.
NOTE
Once the heat pump, heating circuit and
domestic hot water charging circuit have been
flushed, the bleeding program of the heating
and heat pump controller must be started,
after the control panel has been installed.
If no further steps follow, install the front panel.
25 Insulating the
hydraulic connections
NOTE
Insulate the heating circuit and the heat
source according to relevant local standards
and guidelines.
Check all hydraulic connections for leaks. Perform
leak test.
Insulate all connections, vibration isolators, con-
nections and pipes of the heating circuit and the
heat source. Insulate the heat source so that it is
vapour-diffusion tight
.
26 Installing the control panel
There are 4 each recesses at different heights in the
front panel of the unit for fastening the control panel:
1 four upper recesses
2 four lower recesses
There are 4 hooks at the rear of the control panel,
which are used to hook the control panel on the front
panel of the unit:
Hook the control panel's hooks into the recesses
of the front panel (either in the upper or lower
recesses).
Example:
Control panel in upper recesses