Commissioning
9.1
Checking Before Power-On
No. Check Item
Acceptance Criteria
1
Mounting environment
The mounting space is proper, and the mounting
environment is clean and tidy, without foreign object.
2
Battery pack and
inverter mounting
The battery pack and inverter are mounted correctly,
securely, and reliably.
3
WiFi mounting
The WiFi module is mounted correctly, securely, and
reliably.
4
Cable layout
Cables are routed properly as required by the
customer.
5
Cable tie
Cable ties are secured evenly and no burr exists.
6
Grounding
The ground cable is connected correctly, securely,
and reliably.
7
Switch and breakers
status
The PV switch and battery breakers and all the
breakers connecting to the product are OFF.
8
Cable connections
The AC cable, PV cable, battery cable, and
communication cables are connected correctly,
securely, and reliably.
9
Unused power
terminals
Unused power terminals are blocked by
watertight caps.