09 Commissioning
9.1
Checking Before Power-On
No.
Check Item
Acceptance Criteria
1
Mounting environment
The mounting space is proper, and the mounting
environment is clean and tidy, without foreign object.
2
Battery pack and
inverter mounting
The battery pack and inverter are mounted
correctly, securely, and reliably.
3
Wi-Fi mounting
The Wi-Fi module is mounted correctly,
securely, and reliably.
4
Cable layout
Cables are routed properly as required by the customer.
5
Cable tie
Cable ties are secured evenly and no burr exists.
6
Grounding
The ground cable is connected correctly, securely, and
reliably.
7
Switch and breakers status
The PV switch and battery breakers and all the
breakers connecting to the product are OFF.
8
Cable connections
The AC cable, PV cable, battery cable, and
communication cables are connected correctly,
securely, and reliably.
9
Unused power
terminals
Unused power terminals are blocked by
watertight caps.
9.2
Configuring the Safety Standard
Please set the safety standard appropriate for your country or purpose via APP or Web
during pilot run.
The safety standard must be set correctly
If you select a safety standard which is not valid for your country and purpose, it can
cause a disturbance in the energy storage system and lead to problems with the grid
operator. When selecting the safety standard, you must always observe the locally
applicable standards and directives as well as the properties of the PV system (e.g. PV
system size, grid-connection point).
•
If you are not sure which safety standard is valid for your country or purpose, contact
your grid operator for information on which safety standard is to be configured.