ASDI Operations and Maintenance – TX Models – P/N: 52368
3-10
GENERAL
Install the ASDI TORREXX vaporizer on a level firm base at least 6” above grade
and secure it through the four ½” holes. Protect the equipment against damage
by moving vehicles by use of an appropriate barrier. Consult state, provincial,
insurance carriers, and local authorities for installation requirements. Clean all
foreign material from all pipelines prior to making final connections. All joints
require a pipe sealant approved for LPG, depending on type of service. Test for
leaks using an inert gas, such as compressed carbon dioxide or nitrogen, at 1½
times the working pressure or as required by applicable codes. Check all
connections using an appropriate leak detection solution or device. Even very
small leaks are unacceptable. Eliminate all leaks prior to operation.
Install in accordance with applicable codes and local regulations as required.
Explosion proof seal off must carry the same approvals as the vaporizer in
order to maintain the approval of the overall installation.
Figure 5 - Typical TORREXX Installation Drawing with Pump & Vapor Bypass
Note: The vapor bypass line is not required except when you have the Economy
Operation option. In other installations, it is recommended because it will provide
vapor from the tank to the load in case of vaporizer failure or power failure but it
is not required. Vaporizer will operate properly without the bypass.
TANK VAPOR
PRESSURE
REGULATOR*
ISOLATION
VALVE*
VAPOR BY-PASS LINE
OPTIONAL
LIQUID
PRESSURE GAUGE*
VAPORIZER REGULATOR*
STRAINER WITH
MAGNET FOR IRON
PARTICLE PICK-UP*
SEAL OFF REQUIRED*
ELECTRIC SERVICE
REQUIRED*
OUTLET ISOLATION
VALVE”
(VAPOR)
TO LOAD
STORAGE TANK
ISOLATION VALVE
W/HYDROSTATIC
RELIEF*
NOTES
1.
LIQUID PIPING LOSSES BETWEEN VAPORIZER AND THE TANK
MUST NOT EXCEED HYDROSTATIC HEAD WHEN THE PUMP IS
SHUT OFF.
2.
INSTALL VAPORIZER 1
ST
STAGE REGULATOR UPSTREAM OF
THE TANK VAPOR PRESSSURE CONNECTION POINT.
3.
SET 1
ST
STAGE VAPORIZER REULATOR 2-4 PSIG HIGHER THAN
TANK VAPOR PRESSURE REGULATOR SET-POINT.
4.
NO CHECK VALVES IN LIQUID LINE. LIQUID MUST BE ABLE TO
FLOW IN BOTH DIRECTIONS.
*BY OTHERS
ISOLATION
VALVE*
Содержание TORREXX TX100
Страница 8: ......
Страница 56: ...APPENDIX A TECHNICAL INFORMATION ...
Страница 65: ......
Страница 66: ......
Страница 67: ......
Страница 68: ......
Страница 69: ......
Страница 70: ......
Страница 71: ......
Страница 72: ......
Страница 73: ......
Страница 74: ......
Страница 83: ...ASCO Valve used by Algas SDI ...
Страница 86: ...ASCO Valve used by Algas SDI ...
Страница 87: ......
Страница 88: ......
Страница 89: ......
Страница 90: ......