Assembly
5.5.2
Roof frame - floor assembly version without unit frame profile
5.5.2.1 Roof frame preassembled on-site
4
3
2
3
5
6
7
8
6
1
Fig. 32 Roof frame preassembled on-site
1
Foundation
5
Sheet metal apron (on-site installation)
2
Roof frame
6
On-site insulation
3
Sealing compound
7
Z-bracket (on-site installation)
4
Base frame
8
Drilling screw with EPDM washer
Step
Action
1
Place the roof frame (2) onto the foundation (1).
2
Screw the roof frame (2) to the foundation (1) and tie it into the building potential.
3
Apply the sealing compound (3) to the roof frame (2).
4
Place the units onto the roof frame (2) via crane transport.
5
Screw the unit base frame (4) to the roof frame and integrate the AT4F ATEX unit into the building potential.
6
Screw the supplied Z bracket (7) to the base frame (4).
7
Attach the on-site insulation (6) in the area of the roof frame (2) and base frame (4).
8
Pull up the on-site roof membrane for sealing on the roof frame (2) and glue the raised roofing membrane onto the Z
bracket (7).
NOTE: If no sheet metal apron (5) is used, the roof membrane must be pulled up to below the upper base frame mem
-
ber (4) and glued to it.
9
For the installation of the sheet metal apron (5, optional accessories), apply the sealing compound (3) in advance to the
corners of the upper base frame member (4).
Then press the upper flange of the sheet metal apron (5) into the sealing compound (3).
10
Screw the sheet metal apron (5) onto the Z bracket (7). To do this, use the drilling screws with the EPDM washer (8).
The openings for this are pre-punched.
Also integrate the cover plate into the unit/building potential.