AirSynergy 2000 Installation Guide
Page 43
Commercial in Confidence
UGD-D01001 Rev B
Figure 33 - DC Power connection
Figure 34 - Power connection - AirSynergy bottom panel
Advice:
It is good practice to label both ends of the cable to identify which
AirSynergy unit it is connected to. This is especially important where numerous
AirSynergy units are installed on the same pole/tower.
Advice:
It is good practice to leave a spare loop of cable (approximately 0.5m).
This will allow for easier wiring to the power supply and will allow the cable to be
re-terminated if necessary in the future.
7.2.2 Network Cable Installation
For installations that require a network connection a separate cable must be run to the network
Ethernet switch. The standard length of pre-made cable is 30m. For other lengths up to a
maximum of 100m cables can be made up on site.
Advice:
It is good practice to label both ends of the Network cable to identify
which AirSynergy unit it is connected to. This is especially important where
numerous AirSynergy units are installed on the same pole/tower.
Advice:
It is good practice to leave a spare loop of network cable (approximately
0.5m). This will allow for easier wiring to the Network switch and will allow the
cable to be re-terminated if necessary in the future.