Start-Up Procedure
At any point during the process of startup or shutdown, you notice anything unusual; we recommend you
refer to the operation manual immediately. If you cannot find the answer in the troubleshooting section,
contact your Aircel representative or the factory at once.
1. Ensure that the dryer is connected to a
suitable compressed air supply. Make sure
that the pressure of the supply is equal to
the normal operating pressure of the dryer.
2. Check to make sure the “shut-off’ valves
are closed and that by-pass valve is open.
3. Close all manual drain/vent valves.
4. Slowly pressurize the dryer by gradually
(slowly) opening the inlet shut-off valve to
the OPEN position.
5. When both towers of the dryer are
completely pressurized, check the complete
system for possible air leaks. Use soap
and water to test all joints and fittings.
If any leaks are detected, immediately
depressurize the unit and correct the leaks.
6. Make certain that any automatic
condensate drain isolation valves are in
the open position so proper condensate
draining can occur.
7. When normal operating pressure is
reached, switch on electrical power (Turn
switch to ON position)
8. With by-pass valve closed, open the outlet
valve slowly to allow air downstream.
9. When energized one of the towers should
depressurize.
10. Check the operation of several cycles
completely by following the control panel
display screen operation, the panel lights
on the electrical box, and the tower
pressure gauges to make certain the dryer
system is operating as displayed. Also
refer to the how it works section, flow
diagram, electrical drawing, dryer control
display screen descriptions, and sequence of
operation in this manual for reference.
11. Check the drain valve for proper operation
and discharge of liquid (filters and
separators, etc.).
12. Near the dryer outlet (APV) valve, check
the control air/ pilot air regulator secondary
pressure, the regulator gauge should read
100 psig. Increase or decrease regulator
knob to achieve a 100 psig control air
secondary pressure reading.
13. Make certain the purge exhaust valves
slowly open within an 8 to 12 second time
period, some adjustment of the flow control
valve attached to the actuator may be
required, after adjustment tighten down the
locking collar.
14.
Make certain a slight amount of air flow is felt
at the end of the Dew Point Sensor (if aplicable).
Adjust the needle valve, as needed, for more or
less flow. Typical flow is +/- .1 SCFM.
15. Review the dryer system display screen
shots (in this manual) to make certain
the parameters are set as needed in the
customer dryer.
16. Purge air flow is preset and not adjustable.
After the initial startup, the dryer operation is completely automatic. To understand the details of the
operation, we recommend you use the how it works section, flow diagram, electrical drawing, dryer control
display screen descriptions, and sequence of operation in this manual for reference.
Aircel
C
DP-Series Models 70 - 500