POST INSTALLATION CHECK
Make Sure Everything Is Running Properly
After your
AIRSTAR
has been installed and before it is put into operation, be sure to follow
the check-out procedure detailed below:
Check that Intake Filter(s) are fully seated into the compressor head(s) and that the Tank
Outlet Valve is closed .
Turn on the electricity . Check the incoming line voltage . It should be at least 198 Volts
for the AS12INT, AS12CINT AS22INT, AS22CINT, AS50INT, AS50CINT and AS70INT .
This voltage should remain at or above this level while the
AIRSTAR
is running . If
not, install the appropriate boost transformer and check that the correct main circuit
breaker and wire size are being used .
Check pump-up and recovery times .
Turn on the
AIRSTAR
’s power and determine the pump-up time from 0 to 115 PSI .
Drain the storage tank to 80 PSI and determine the recovery time from 85 to 115 PSI .
If the pump-up or recovery time exceeds the duration listed by the table below, call an
authorized dealer for service .
INSTALLATION INFORMATION
Model
Number of
Motors/Heads
Maximum
Pump-up Time
0-115 PSI
(M:SS)
Maximum
Recovery Time
85-115 PSI
(M:SS)
AS12INT
1/1
2:55
0:48
AS22INT
1/2
3:10
0:47
AS50INT
2/4
2:50
0:42
AS70INT
3/6
2:40
0:40