17
7.6 Re-air purging (Re-installation)
Procedure:
1. Confirm that both the 2-way and 3-way valves are set to the closed position.
2. Connect the charge set and a charging cylinder to the service port of the 3-way valve.
Leave the valve on the charging cylinder closed.
3. Air purging.
Open the valves on the charging cylinder and the charge set. Purge the air by loosening the flare nut on the
2-way valve approximately 45’ for 3 seconds then closing it for 1 minute; repeat 3 times.
After purging the air, use a torque wrench to tighten the flare nut to on the 2-way valve.
4. Check the gas leakage.
Check the flare connections for gas leakage.
5. Discharge the refrigerant.
Close the valve on the charging cylinder and discharge the refrigerant until the gauge indicates 0.3 to 0.5 Mpa.
6. Disconnect the charge set and the charging cylinder, and set the 2-way and 3-way valves to the open position.
Be sure to use a hexagonal wrench to operate the valve stems.
7. Mount the valve stems nuts and the service port cap.
Be sure to use a torque wrench to tighten the service port cap to a torque 18N.m.
Be sure to check the gas leakage.
Содержание A17CI4C4M09
Страница 10: ...8 4 Specification Please see the special file about the specifications 5 Refrigerant cycle diagram Cooling only...
Страница 11: ...9 6 Wiring diagram 6 1 Indoor Unit MSC 09CRDN1 NR0 MSC 12CRDN1 NR0 MSC 18CRDN1 NQ0...
Страница 12: ...10 MSC 24CRDN1 NQ0W 6 2 Outdoor Unit MOA 09CDN1 NR0...
Страница 13: ...11 MOB 12CDN1 NR0...
Страница 14: ...12 MOC 18CDN1 NQ0...
Страница 35: ...33 K...