TANK INSTALLATION 

 

IMPORTANT: The tank / IBC owner and user(s) are fully responsible for environmental contamination, 

clean up and/or unsafe or explosion hazards as a result of improper installation, use, or maintenance of 

this tank. 

 

It is the requirement of the tank owner /  installer /  user(s) to: 

a.

 

Ensure that all federal, provincial, and local codes and regulations are met prior to tank installation. Examples include, 

but are not limited to, Fire and Environmental Codes. Consult the authority having jurisdiction to be certain. 

b.

 

Ensure that the truck or trailer being used is capable of carrying the weight of the tank plus the weight of the fuel, 

calculated on the maximum listed capacity of the tank. 

c.

 

Ensure that the mounting location on the truck or trailer platform is capable of bearing the total weight transfer of the 

tank plus the maximum weight of the loaded fuel, and the load transfer of the fuel to the hold down straps as the load 

shifts during transport. 

d.

 

Unless tank is equipped with Wet Lugs (Shown in Figure 1: Optional Equipment for RV290-830 tanks), ensure tank is 

completely empty prior to lifting. All tanks must also be free of hold down anchors prior to lifting. If relocating to 

another form of transport, ensure points a, b and c are followed again. 

 

Anchoring installation

 

(see Figure 1 to determine which method is applicable to the tank model being installed) 

1.

 

Steel Strap Installation:  Locate the hold-down straps and neoprene pads so that each strap is flat against the tank 

as shown in Figure 1. The neoprene pad is to be installed under each hold-down strap prior to tightening. 

Hold-down 

straps are NOT to be welded to the tank /  IBC in any manner. 

2.

 

J-Bolt Installation: Locate the Base Brackets, D-rings, J-Bolts and neoprene pads as shown in Figure 1. The neoprene 

pad is to be installed between the base bracket and bottom of the tank. 

Use a minimum of 15 ft-lb torque to 

fasten the nuts on the j-bolts. 

3.

 

Ratchet strap installation: Locate the D-ring brackets as close to the tank shell as possible and mount to the truck 

bed using the hardware provided.  To prevent lateral movement of the tank during transport, the straps can be angled 

around the pump and fill fitting as shown in Figure 1.

 

4.

 

 

Before drilling any holes, ensure that no critical locations such as frame, fuel lines, brake lines or 

electrical lines are affected.  

DO NOT drill through the truck frame, as this can lead to frame cracking or 

failure with potential to cause serious injury or death.  Drill holes through truck box or deck floor only. 

Ensure that the IBC is properly secured to the platform or deck using the hold down straps and hardware supplied.

 

5.

 

Roll Guards are supplied in some parts kits for protection of the pump and must be mounted to the tank using the 

hardware supplied.  Where a pump box assembly is used, only one guard is necessary.

 

6.

 

If the tank / IBC is equipped with a discharge pump, it must not weigh more than 12 kg (not including hose and 

nozzle), be able to withstand 200 kPa (29 PSI) and have a shut-off valve on the outlet side, or the pump must be 

isolated from the tank by a valve which can be closed off in an effective manner.  

During transport, the valve must 

be in a closed position.

 

7.

 

Before filling the tank (either fully or partially) with flammable liquids, ensure that a ‘Transport of Dangerous Goods 

Decal for Flammable Liquids’ is installed (see page 4).

 Moving the tank and/ or the vehicle carrying this tank in 

any manner without this decal is a violation of Transport Canada requirements. This decal is the 

responsibility of the tank owner and is not provided by Westeel. Consult distributor or Safety Supply Store for availability 

and requirements

 

8.

 

Once the tank is installed as described above, fill the tank with fuel and mark the position of the straps on the tank with 

a water soluble marker. Go on a trial road trip, frequently stopping the vehicle and checking the position changes of 

straps with respect to the marked tank. The position should not change. 

Re-tighten strap nuts after a few days of use. 

Be sure to check straps periodically to ensure tank remains secure.

 

9.

 

On a yearly basis, check all parts, including paint, for damage. Touch up paint scratches and chips using compatible 

enamel paint. Maintaining the paint coating on the tank helps prevent rust from forming. Rust can increase the likeliness 

of tank failure and / or reduce the useable life of the tank.

 

 

 

Содержание WESTEEL ROAD VAULT

Страница 1: ...P N 198804_IBC REV 06 Printed in Canada Revised 15 Oct 19 Mobile Petroleum Tank READ THESE INSTRUCTIONS CAREFULLY AND COMPLETELY BEFORE INSTALLATION AND USE OF TANK...

Страница 2: ...osion 5 Internal Corrosion 5 Loss of Vacuum 5 Underground Tanks 5 General Disclaimers 5 DESIGN USE 6 General 6 Non Code Portable Service Tank 6 Road Vault Service Tank IBC 6 SHORTAGES DAMAGED PARTS AN...

Страница 3: ...MERGENCY VENT P N 264639 AT EMERGENCY VENT P N 530162 TRANSPORT CANADA PRODUCT IDENTIFICATION DECAL NOT SUPPLIED BY WESTEEL SERIAL NUMBER DECAL P N 198870 INSPECTION LABEL ROAD VAULT LOGO DECAL P N 26...

Страница 4: ...r assembly iv any use of the goods which is not an intended use as specified in Westeel s published product literature or otherwise specified by Westeel in writing v any equipment attached to or used...

Страница 5: ...d accepted trade practices Without limiting the generality of the foregoing proper foundation assembly installation and use solely for the purposes intended as specified in Westeel s published product...

Страница 6: ...Service Tank Mobile IBC These tanks are designed in accordance with United Nations Transport Canada Regulations and the Canadian General Standards Board code CAN CGSB 43 146 for use as mobile intermed...

Страница 7: ...movement of the tank during transport the straps can be angled around the pump and fill fitting as shown in Figure 1 4 Before drilling any holes ensure that no critical locations such as frame fuel l...

Страница 8: ...8 FIGURE 1 TANK INSTALLATION DIAGRAMS Flat Top Design L Tank Models RV285 290 450 545 680 830 Ratchet strap available on Optional Equipment for RV290 830 Models...

Страница 9: ...ring testing While under the test pressure each container shall be visually inspected for leakage defective fittings welds or closures structural components significant gouges or other defects Non int...

Страница 10: ...stallation with a wrench or pipe joint sealant for normal use Emergency Vents Fusible Plug Mobile IBC Tanks are factory fitted with an emergency vent in any one of the styles shown below FUSIBLE DISC...

Страница 11: ...No de pi ce 198804_IBC r v 06 Imprim au Canada R vis le 15 Octobre 2019 R servoir de p trole mobile LIRE CES CONSIGNES SOIGNEUSEMENT ET ENTI REMENT AVANT L INSTALLATION ET L UTILISATION DU R SERVOIR...

Страница 12: ...gations g n rales de responsabilit 5 CONCEPT ET UTILISATION 6 G n ralit s 6 R servoir de service portatif non r glement 6 R servoir de service Road Vault GRV 6 PI CES MANQUANTES ENDOMMAG ES ET QUIPEME...

Страница 13: ...E PRESSION No de pi ce 530162 D CALCOMANIE D IDENTIFICATION DE PRODUIT DE TRANSPORTS CANADA NON FOURNI PAR WESTEEL NUM RO DE S RIE DE D CALCOMANIE No de pi ce 198870 TIQUETTE D INSPECTION REQUIS AU DE...

Страница 14: ...pr vue tel que sp cifi dans la brochure publi e du produit ou autrement sp cifi par crit pas Westeel v tout quipement fix aux articles ou utilis en conjonction avec ceux ci vi toute modification sur l...

Страница 15: ...age de fondation ad quat l installation et l utilisation uniquement aux fins pr vues et sp cifi es dans la brochure publi e du produit sont essentiels De plus la ventilation du r servoir pour les situ...

Страница 16: ...ts R servoir de service Road Vault GRV Ces r servoirs sont con us conform ment aux r glements de l Organisation des Nations Unies et de Transports Canada et la norme CAN CGSB 43 146 de l Office des no...

Страница 17: ...s peuvent tre inclin es autour de la pompe et l accessoire de remplissage tel qu illustr la figure 1 4 Avant de percer des trous s assurer qu aucun endroit critique tel que le ch ssis les conduits de...

Страница 18: ...MES D INSTALLATION DU R SERVOIR Conception dessus plat Conception de r servoir Mod les RV285 290 450 545 680 et 830 Sangle cliquet disponible pour les mod les RV285 et 450 quipement en option pour les...

Страница 19: ...t en v rification de pression chaque r cipient doit tre visuellement inspect pour d celer la pr sence de fuites de raccords d fectueux de soudures ou de fermetures de composants structurels d importan...

Страница 20: ...usage normal vents d urgence bouchon fusible Les r servoirs GRV mobiles sont quip s en usine d un vent d urgence dans l un ou l autre des styles montr s ci dessous DISQUE DE BOUCHON FUSIBLE BOUCHON F...

Страница 21: ...E DEPTH PROFONDEUR VOLUME cm litres cm litres cm litres cm litres 1 12 22 275 43 540 64 804 2 23 23 288 44 552 65 817 3 36 24 300 45 565 66 829 4 49 25 313 46 577 67 842 5 61 26 326 47 590 68 854 6 74...

Страница 22: ...3 79 1 511 114 2 170 10 85 45 735 80 1 533 115 2 183 11 98 46 757 81 1 555 116 2 195 12 111 47 780 82 1 577 117 2 207 13 125 48 802 83 1 599 118 2 218 14 139 49 825 84 1 621 119 2 228 15 154 50 847 85...

Страница 23: ...4273 9 144 44 1410 79 2990 114 4300 10 168 45 1454 80 3034 115 4325 11 193 46 1498 81 3077 116 4350 12 220 47 1542 82 3121 117 4373 13 247 48 1587 83 3164 118 4395 14 276 49 1631 84 3208 119 4416 15...

Страница 24: ...7 113 1984 9 67 44 654 79 1388 114 1996 10 78 45 675 80 1408 115 2008 11 90 46 695 81 1428 116 2020 12 102 47 716 82 1449 117 2031 13 115 48 736 83 1469 118 2041 14 128 49 757 84 1489 119 2051 15 141...

Страница 25: ...113 4113 9 139 44 1362 79 2884 114 4138 10 162 45 1404 80 2926 115 4162 11 187 46 1446 81 2968 116 4185 12 212 47 1489 82 3010 117 4207 13 239 48 1532 83 3052 118 4228 14 266 49 1575 84 3093 119 4247...

Отзывы: