Chapter 2: 6' Peak Handrail Kit Installation
4. Install the first two toe boards (5) to the peak handrail post (4) using 5/16" flange bolts (20) and
5/16" flange nuts (23). Continue overlapping the toe boards in the same way as you work your way
around the peak.
NOTE:
The bolt (20) head must be installed towards the walking area.
NOTE:
The 54' uses the outside set of holes and the 60' uses the middle set of holes.
Figure 2-4
Toe board alignment for the 54' and 60' bins
14
PNEG-2041
6', 10' and 14' Peak Handrail Kits