Mounting and commissioning
ProCalida® GT 3
25
7.
Repeat the procedure (filling and flushing, step 3.-5.) for all oth-
er heating circuits.
Vent
Drain the system at the boiler filling and drain valve KFE of the
flow, if required.
5.6
Performing the pressure test and the function test
1.
Apply 6 bar of pressure to the system for a period of 2 hours
(max. 30 °C).
2.
Perform a leak test after 2 hours.
The pressure drop must not exceed 0.2 bar.
3.
Fill the system with the fluid until the operating pressure is
reached.
Содержание ProCalida GT 3
Страница 14: ...Technical specifications 14 ProCalida GT 3 Fig 11 Pressure loss curves with flow meter 2 12 l min ...
Страница 15: ...Technical specifications ProCalida GT 3 15 Fig 12 Pressure loss curves with flow meter 5 42 l min ...
Страница 16: ...Technical specifications 16 ProCalida GT 3 Fig 13 Pressure loss curves with flow meter 35 70 l min ...
Страница 17: ...Technical specifications ProCalida GT 3 17 Fig 14 Pressure loss curves with flow meter 60 125 l min ...