14
Installation
3,41 Installing the ACO Self®
Europoint Deep/Round
Create installation space/ lay KG pipe:
Create installation space (on-site)
(approx. 0.5 m x 0.5 m x 1.0 m)
Increase the installation space accor-
dingly when intermediate elements
are utilised.
One intermediate part
+ 277 mm
Two intermediate parts
+ 554 mm
KG pipe (collar 110 mm) for Euro-
point horizontal connection.
Installation space dimensions:
Without intermediate section
= 553 - 528 mm
One intermediate section
= 830 - 805 mm
Two intermediate sections
= 1100 - 1075 mm
below the sur-
face.
Install point outlet:
Create the foundation. Foundation
concrete quality minimum
C12/15 (1).
Position Europoint Deep/Round and
align it (2).
Grease the KG pipe (3).
Insert into the seal up to the stop end
(approx. 3 mm) (4).
4.
2.
3.
1.