9
Installation
1 = Grating
2 = ACO Self® Europoint Flat, small
3 = KG pipe DN/OD110
4 = Sand
5 = Concrete
6 = Pavior bedding*)
7 = Rectangular concrete paviors
* Sand, gravel or grit bedding (unbound construction method = standard construction
method according to ZTV P StB9).
2.
1.
max. 60 mm
3.21 Installing the ACO Self®
Europoint Flat
Create installation space:
Create installation space (on-site)
(approx. 0.5m x 0.5m x 0.5m).
KG pipe (collar 110 mm) for Euro
point vertical connection.
KG pipe (socket 110 mm) for vertical
standard point connection.
Compact the substrate with sand
(bedding material as sand 0/8).
Install point outlet:
Grease the socket (1).
Attach Europoint Flat with grating
and align (approx. 3-5 mm below the
adjacent surface e.g. paviors) (2).
Alignment to the pavior pattern is
possible, 360° rotatable.
Fill in concrete up to maximum 60 mm
below the surface. Foundation con-
crete as concrete quality C12/15.
Lay the paviors (wet in wet).