O PER AT I O N , M A I N T EN A N C E , A N D I N S TA L L AT I O N G U I D E
2.5.2 Switching sequence / Automatic
(Closed transition)
2.5.2.1 SOURCE 1 Priority
(SOURCE 2 = Generator)
The switching sequence can be
summarized in the following steps:
1. Activate test on load (HMI or digital
input)
2. Generator start
3. Run engine warm-up timer
4. Pre-transfer S1 to S2 delay
5. Check source synchronization
6. Close SOURCE 2 contacts
7. Open SOURCE 1 contacts, start ETT
timer (parallel mode)
8. Post-transfer S1 to S2 delay
The re-transfer sequence can be summa-
rized in the following steps:
1. Cancel test on load (HMI or digital
input)
2. SOURCE 1 availability timer
3. Pre-transfer S2 to S1 delay
4. Check source synchronization
5. Close SOURCE 1 contacts
6. Open SOURCE 2 contacts, start ETT
timer (parallel mode)
7. Post-transfer S2 to S1 delay
8. Run engine cool down timer
9. Generator stop
Содержание Zenith ZTS T Series
Страница 2: ...2 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 6: ...6 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 10: ...10 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 36: ...36 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 44: ...44 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 105: ...105 1 OPER ATION MAINTENANCE AND INSTALL ATION GUIDE Fig 7 9 Figure B C A B Fig 7 8 Figure A A B C ...
Страница 106: ...106 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 108: ...108 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 114: ...2 114 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A Fig 9 5 9 6 R5 Lifting points ...
Страница 122: ...2 122 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 126: ...2 126 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 129: ...129 1 OPER ATION MAINTENANCE AND INSTALL ATION GUIDE ...