O PER AT I O N , M A I N T EN A N C E , A N D I N S TA L L AT I O N G U I D E
—
9.7 Initial Energizing
Before proceeding, refer to the informa-
tion package supplied with the ATS and
read and understand the information on
all accessories provided, including this
complete document.
Before energizing the panel
1. Confirm that installation has been
performed by a qualified person and in
accordance with NFPA 70 (NEC).
2. Confirm rating label matches the in-
stalled application. Rating label is lo-
cated inside the panel enclosure.
3. Confirm that cables are connected
properly and torqued according to the
ATS labeling.
4. Verify that the enclosure ground con-
nection is properly terminated.
5. Confirm that control wiring for engine
start is properly terminated to the en-
gine start contact (located in Fig. 2.1,
number 8). Additionally, connect all
applicable digital I/O, communications,
and auxiliary contact wiring.
6. Flip slide switch (Fig. 2.1, number 4)
to AUTO.
7. Ensure that all objects and debris are
removed from enclosure, and enclosure
is closed and latched.
Energizing the panel
1. Close Source 1 circuit breaker.
NOTE:
The HMI should illuminate if line
voltage is present and S1 LED should
light up.
2. Verify the phase to phase voltages at
the Source 1 terminals.
3. Initiate auto configure from HMI default
screen: Main Menu > Parameters >
System Parameters > Start Automatic
Configuration and allow a few seconds
for system parameters to set"
4. Close the Source 2 circuit breaker.
5. Start the generator engine.
NOTE:
If generator voltage is present at
Source 2 terminals, S2 LED should light
up.
6. Verify phase rotation of S1 matches
that of S2.
NOTE:
The ATS will not allow transfer if
phase rotation does not match.
7. Shut down the generator engine.
8. For additional start-up guidance for the
ATS, please refer to ZTS Mini Manual,
document number 1SCC301108M0201.
Notice
This installation should be properly operated
and maintained in accordance with the safety
practices of NFPA 70E.
Содержание Zenith ZTS T Series
Страница 2: ...2 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 6: ...6 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 10: ...10 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 36: ...36 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 44: ...44 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 105: ...105 1 OPER ATION MAINTENANCE AND INSTALL ATION GUIDE Fig 7 9 Figure B C A B Fig 7 8 Figure A A B C ...
Страница 106: ...106 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 108: ...108 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 114: ...2 114 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A Fig 9 5 9 6 R5 Lifting points ...
Страница 122: ...2 122 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 126: ...2 126 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Страница 129: ...129 1 OPER ATION MAINTENANCE AND INSTALL ATION GUIDE ...