background image

16

VD4 -3 6 K V CR A DLE R ETROFIT SOLUTION 

SER V I C E  I N S T R U C T I O N  M A N UA L

Putting into service

General procedures

Wiring of auxiliary circuit

The auxiliary circuits of the withdrawable circuit- breaker 
are fully cabled from the factory up to male connector.

For the external connections, please refer to the electric 
diagram of the enclosure or of the switchgear. The female 
connector in the existing panel must be replaced with the 
corresponding female connector suitable for male 
connector of CB & cabling of the panel to be done up to the 
female connector during installation.

Before putting the circuit-breaker into service, carry out 
the following operations:

•  Check the tightness of the power connections on the 

circuit-breaker terminals

•  Establish the setting of the direct solid-state overcurrent 

release (if provided)

•  Check that the value of the supply voltage for the 

auxiliary circuits is within 85% and 110% of the rated 
voltage of the electrical devices

•  Check that no foreign body, such as bit of packaging, has 

got into the moving parts

•  Check that air circulation at the circuit-breaker 

installation site is adequate so that there is no danger of 
overheating

•  Carry out the checks indicated in table 2.1 (see page 17)

CAUTION

During installation of VD4 CB first time with 
existing panel, before inserting VD4 CB inside 
cubicle ensure that power supply to the panel is 
completely switched off and there is no residual 
charge present on cubicle contact by use of 
proper earthing

CAUTION

All the operations regarding putting into 
service must be carried out by ABB personnel or 
personnel who are suitably qualified and have 
in- depth knowledge of the apparatus and 
installation. If the operations are prevented, do 
not force the mechanical interlocks, but check 
that the operation sequence is correct

The racking-in/-out operations must always be carried out 
with the circuit-breaker open.

While putting into service for the first time, before 
connecting secondary plug with panel socket, it is advisable 
to charge the circuit- breaker operating mechanisms 
manually so as not to overload the auxiliary power supply 
circuit.

When the CB is inserted in the in the guide fixed on panel 
side, check the following:
•  Free movement of breaker from test to service position 

and vice versa

•  Proper engagement of secondary plug and socket
•  Proper functioning of various interlocks
•  Proper engagement of earthing contact
•  Proper engagement of VCB tulip contact with cubicle  

pin contact

Содержание VD4 Series

Страница 1: ...6 gas CB HPA36 Addendum to VD4 installation operation and maintenance manual DISTRIBUTION SOLUTIONS VD4 36kV vacuum CB cradle solutions for retrofitting SF6 gas CB HPA36 Addendum to VD4 installation o...

Страница 2: ...4 36kV cradle retrofit solution makes the use of fixed VD4 type of circuit breaker For this reason most of the information contained in the VD4 instruction manual is also effective for this retrofit s...

Страница 3: ...fit solution 06 Specific VD4 36kV cradle retrofit instructions 06 Packing transport 06 Handling 07 Handling with slings 08 Handling with trolley 09 10 Description 11 12 Instruction for VD4 CB operatio...

Страница 4: ...on of cradle retrofit solutions require modification in existing VHA 36 switchgear panel However this apparatus allows further technical construction modifications at the customer s request to adapt t...

Страница 5: ...nce standard Section 5 3 EL operating mechanism Section 5 4 Fixed circuit breaker Section 5 4 1 General characteristics of fixed circuit breakers 36Kv Section 5 4 2 Type of circuit breakers available...

Страница 6: ...t all the materials described in the shipping notes are including in the supply Should any damage or irregularity be noted in the supply on packing notify ABB directly or through the agent or supplier...

Страница 7: ...ndling not to stress the insulating parts and the circuit breaker terminals Fig 7 1 Fig 7 2 Fig 7 3 In any case it is always advisable to carry out lifting using the supports figure 7 4 8 1 in positio...

Страница 8: ...ing platform can be moved up down depending on the direction of rotation of the handle Fig 8 1 In order to insert circuit breaker into the VHA 36 panel position the trolley in front of the panel lift...

Страница 9: ...ers withdrawable version The VD4 36kV cradle retrofit solution is specifically used for retrofitting SF6 gas circuit breakers HPA36 in ABB make VHA36 panels The circuit breaker is having three pole as...

Страница 10: ...SE 4 Indication for closing spring charged discharged 5 Operation counter 6 Lever for manually charging the closing spring 7 Rating plate 8 Earthing contact 9 Common truck 10 Cable stem 11 Coil suppor...

Страница 11: ...s figure 11 1 Legends of figure 11 1 1 Front cover 2 Opening push button 3 Closing push button 4 Indication for circuit breaker OPEN CLOSE 5 Indication for closing spring charged discharged 6 Operatio...

Страница 12: ...rcuit breaker closing The operation can only be carried out with the closing spring completely charged For manual closing press the push button 3 figure 11 1 When there is a shunt closing release the...

Страница 13: ...assembly after preparing it along with guide rails guide brackets and earth guides Rear bottom plate of CB compartment Top cover upper door assembly above CB compartment main door CB compartment main...

Страница 14: ...14 1 2 Fig 14 2 Legends of fig 14 1 and 14 2 1 SF6 circuit breaker HPA36 2 CB compartment door top 3 CB compartment main door 4 Bottom front door 3 4 Fig 14 4 1 2 3 1 24 pin socket 2 Emergency trip as...

Страница 15: ...plate assembly 2 Earth guide 3 LHS RHS guide rails 4 Rear bottom plate Fig 15 2 1 CB compartment top cover upper door assembly 2 VD4 36kV circuit breaker 3 CB compartment main door 4 Bottom front door...

Страница 16: ...is no danger of overheating Carry out the checks indicated in table 2 1 see page 17 CAUTION During installation of VD4 CB first time with existing panel before inserting VD4 CB inside cubicle ensure t...

Страница 17: ...correctly 4 Motor operator Supply the geared motor for spring charging at the relative rated voltage Carry out a few closing and opening operations N B Supply the undervoltage release and the locking...

Страница 18: ...s discharges or traces of surface discharges 3 Visual inspection of the operating mechanism and transmission 1 year or 5000 operations The elements must be free of any deformation Screws nuts bolts et...

Страница 19: ...Electrical diagram The standard VD4 circuit breaker electric circuit diagram is as follows VD4 electric diagram Each circuit breaker is always provided with the standard electric diagram or with a sp...

Страница 20: ...ated in the technical catalogue and always state the following Type of circuit breaker Rated voltage of the circuit breaker Rated normal current of the circuit breaker Breaking capacity of the circuit...

Страница 21: ...ension and ratings VD4 36kV vacuum circuit breaker cradle retrofit solution VD4 36kV cradle retrofit solution Ur 36kV Ir 1250A Isc 31 5kA 880 984 784 853 946 367 480 114 248 320 4 424 57 736 944 4 102...

Страница 22: ...NSTRUCTION MANUAL Overall dimension and ratings VD4 36kV vacuum circuit breaker cradle retrofit solution VD4 36kV cradle retrofit solution Ur 36kV Ir 2000A Isc 31 5kA 984 853 782 880 253 5 114 947 367...

Страница 23: ......

Страница 24: ...without prior notice With regard to purchase orders the agreed particulars shall prevail ABB does not accept any responsibility whatsoever for potential errors or possible lack of information in this...

Отзывы: