19
1ZSE 5492-128 en, Rev. 4
3 Repairs and adjustments
3. Repairs and adjustments
For
Contact replacement
see Maintenance Guide.
For
Adjustment of Disc Brake
see Maintenance Guide.
For
Replacement of Gasket between on-load tap-changer tank and Transformer
tank
see Installation and Commissioning Guide.
3.1 Replacement of gasket between insulating board and selector switch unit
3.1.1 General
This instruction guides you how to replace the gasket between the insulating board and the
selector switch moulding. The instruction can be used for both
UZE
and
UZF
on-load tap-
changers.
CAUTION
ABB recommends that only maintenance engineers trained by ABB carry out replacement of
gasket between barrier board and selector switch unit.
3.1.2 Tools required
■
Pump with connection fitting the oil valve
■
Box wrench (19 mm)
■
Electric drill, set of drills
■
Thread tap M16
■
Chisel (as used by a woodworker)
■
Dynamometric wrench (up to 42 Nm)
■
Tool with a prolonged shaft for square nuts (27 x 27 mm)
3.1.3 Material and spare parts required
■
Maintenance Guide
■
Clean and empty drums (for oil draining)
■
Rags (not cotton waste)
■
Rope (approximately 2 m)
■
Wooden wedges, made of birch wood or similar, rather hard wood (length approx.
100 mm, width approximately 40 mm, and thickness approximately 20 mm)
■
Ethylacetate or similar solvent
■
Distance pieces of wood or pressboard (thickness of approximately 9 mm)
■
Single-phase diagram valid for the actual on-load tap-changer
■
Glue, nitrile rubber adhesive, preferably of type ”Pliobond 20” (Good Year)
■
Brush for application of adhesive
■
Gasket
■
Grease for ball-bearings
■
Brush for grease
■
Polyvinylacetate adhesive (normal glue for wood)
■
18 stud bolts and 18 nuts
■
Tools and materials for draining transformer oil according to the transformer documen-
tation.
Содержание UZE
Страница 6: ......
Страница 8: ......
Страница 17: ...17 1ZSE 5492 128 en Rev 4 fm_00120 2 Trouble shooting Fig 3 Circuit diagram...
Страница 18: ...18 1ZSE 5492 128 en Rev 4 fm_00113 2 Trouble shooting Fig 4 Contact timing diagram...