Operation Manual / 4 Product description / TPS44-H.. - TPS52-H..
3
Commissioning
Page 20 / 99
© Copyright 2016 ABB. All rights reserved.
HZTL4037_EN
Revision A
August 2016
3.2
Inspection procedures
3.2.1
Introduction
Inspection procedures include preventative visual controls, monitoring and measuring work
before and during commissioning. Inspection procedures enable changes to the turbocharger
to be detected. Engine damage can be prevented.
3.2.2
Checks before commissioning
Filter mat (if available)
Check for damage and contamination.
Lubricating system
CAUTION
Contaminated oil
Serious damage to engine or property can be caused by dirt and solid mate-
rial particles in the oil.
At initial commissioning and after all service work, the complete lubricating
system must be thoroughly flushed with warm oil.
Use special running-in filters when running in the engine and after all ser-
vice work on the lubricating system.
Check that the oil filter is clean before commissioning.
Adhere to lubricating oil pressure at the inlet.
Adhere to lubricating oil temperature at the inlet.
For permissible values, see chapter
Warning plates
Check whether warning plates are present and legible.
Check whether the protective sheets have been removed.