
12
Check-List for Mounting
12-3
Sec. 4.2 Cabling the Ethernet modules
Does a network plan exist (4.2.4)?
Are acceptance measurements planned or have they already been performed
(4.2.4.2)?
Battery: Is a buffer battery installed in the Ethernet module?
Does the buffer battery have the right polarity?
Is an EI 811F, EI 812F, EI 813F or AM 811F module provided
to ensure battery buffering of the PM 803F?
Are routine maintenance intervals planned for the batteries?
Installing a 10Base2 network (4.2.5)
Are both cable ends terminated with the appropriate terminating resistors?
Is the 10Base2 cable grounded at each AC 800F with the appropriate clip?
Is the minimum spacing of 0.5 m between two nodes observed?
Is the max. permissible bus cable length observed?
Branch cables are not permissible. Is this rule observed?
Grounding: Did you avoid shorts to ground? Did you perform the appropriate
measurements to verify?
Were all cables laid and fastened properly. Were the cable shields put on?
Installing a 10Base5 network (4.2.6)
Is the bus cable length a multiple or a combination of the standard lengths?
Is the max. cable length of 500 m observed?
Was the max. cable length confirmed by a TDR measurement record?
Is the cable terminated at each end with the appropriate terminating resistor?
Is the bus cable grounded at exactly one point?
Did you prevent accidental ground fault of the 10Base5 bus cable by insulating
the ungrounded terminating resistor and the N/N connectors?
Are the transceivers attached to the cable at the marks?
Did you measure the resistance at each transceiver with an ohmmeter to see if it
is 25
Ω
between the shield contact and the core, with the terminating resistors
screwed on ?
Is the AUI cable shield put on the contact ledge properly? Did you fasten the
cable with the appropriate clips?
Содержание AC 800F
Страница 1: ... PROCESS AUTOMATION Freelance 2019 Mounting and Installation Instructions AC 800F Controller ...
Страница 2: ......
Страница 66: ...3 Mounting the AC 800F 3 38 ...
Страница 168: ...4 Cabling the AC 800F 4 102 ...
Страница 290: ...7 Functional Description of the Fieldbus Modules 7 36 ...
Страница 317: ...10 Approvals certificates 10 1 10 Approvals certificates 10 1 ISO 9001 Fig 10 1 ISO 9001 ...
Страница 318: ...10 Approvals certificates 10 2 Fig 10 2 ISO 9001 ...
Страница 319: ...10 Approvals certificates 10 3 Fig 10 3 ISO 9001 ...
Страница 320: ...10 Approvals certificates 10 4 Fig 10 4 ISO 9001 ...
Страница 321: ...10 Approvals certificates 10 5 10 2 ISO 9000 Fig 10 5 ISO 9000 ...
Страница 322: ...10 Approvals certificates 10 6 Fig 10 6 ISO 9000 ...
Страница 323: ...10 Approvals certificates 10 7 10 3 CE Fig 10 7 CE certificate page 1 ...
Страница 324: ...10 Approvals certificates 10 8 Fig 10 8 CE certificate page 2 ...
Страница 325: ...10 Approvals certificates 10 9 Fig 10 9 CE certificate page 3 ...
Страница 326: ...10 Approvals certificates 10 10 Fig 10 10CE certificate supplement ...
Страница 327: ...10 Approvals certificates 10 11 10 4 CSA Fig 10 11 CSA certificate page 1 ...
Страница 328: ...10 Approvals certificates 10 12 Fig 10 12 CSA certificate page 2 ...
Страница 329: ...10 Approvals certificates 10 13 Fig 10 13 CSA certificate page 3 ...
Страница 330: ...10 Approvals certificates 10 14 Fig 10 14 CSA certificate page 4 ...
Страница 331: ...10 Approvals certificates 10 15 10 5 UL Fig 10 15 UL certificate ...
Страница 332: ...10 Approvals certificates 10 16 Fig 10 16 UL certificate page 2 ...
Страница 333: ...10 Approvals certificates 10 17 Fig 10 17 UL certificate page 3 ...
Страница 334: ...10 Approvals certificates 10 18 Fig 10 18 UL certificate page 4 ...
Страница 335: ...10 Approvals certificates 10 19 10 6 GUS certificate Fig 10 19 GUS certificate ...
Страница 369: ...13 Glossary 13 18 Component of the Freelance 2000 System ...
Страница 378: ......