Page 19
5.3
Systems outdoor installation
5.3.1
Outdoor installation requirements
CAUTION!
Damage to the system due to tilting of the control cabinet!
Anchoring the earth base in the foundation
Check whether stability is guaranteed
Ensure that heat can be dissipated through adequate air circulation.
Ensure that the door area is freely accessible.
5.3.2
Ground hole for concrete base and GRP base
Generally, the base is anchored in the ground so that tilting and sagging can not be caused.
Work to be carried out:
Dig a 110 cm to 130 cm deep hole in the ground.
Use ballast and gravel and concrete of adequate depth to form a solid foundation.
Level the foundation.
Install the base and fix it with the foundation (stability).
Figure 5-1 Foundation
Special requirements of the GRP-base
The connection profile can not be used due to the transformer block. The side panels must
be fixed with cement or similar.
Figure 5-2 Side panels of the GRP base
Содержание Low Voltage Regulation System
Страница 2: ......
Страница 40: ...Page 38 We take care of it Figure 5 24 Photo instruction use of terminal block 2 ...
Страница 51: ...Page 49 Figure 5 37 Installation thread rods in ring saddle Figure 5 38 Top view pole installation ...
Страница 59: ...Page 57 Figure 6 6 Operation switch disconnector 1 2 3 4 5 Figure 6 7 NH switch disconnectors ...
Страница 63: ...Notes ...