11. 

WAN port indicator (WAN) 

12. 

LAN port indicator (LAN) 

13. 

Bridge signal strength indicator (

14. 

Breather valve 

15. 

Location hole 

Note Before Mounting: 

 

Don't place or install the device in area near water or 
moist, keep the relative humidity of the device 
surrounding between 5%~95% without condensation. 

 

Before power on, first confirm the supported power 
supply specification to avoid over-voltage damaging the 
device.

 

 

The device surface temperature is high after running; 
please don't directly contact to avoid scalding. 

Mounting Dimension

 

Unit: mm 

 

Pole-mounted Device Mounting

 

 

Use 4 M6 screws to install the clamp board as 

Step 1

shown in the figure below on the device backboard. 

 

 

Align the other clamp board with the hole center 

Step 2

line of the installed clamp board, then place the 

support pipe to align the hole center of the two 
clamp boards. When the two clamps are docking, 
you can choose 15° or 90° installation angle. 

 

 

Pass the M6 long screw through the hole where the 

Step 3

clamp boards are docked and the support pipe, and 
tighten the corresponding M6 nut. 

 

 

Install U-shaped derrick screws and derrick teeth 

Step 4

on the clamp board, and put the derrick with a 

diameter of Ф40 mm 

Ф50mm in an U

-shaped slot, 

as shown in the figure below. 

 

 

Adjust device position and tighten the derrick nut to 

Step 5

fix the position of the device on the derrick. 
Installation ends. 

 

Pole-mounted Device Disassembling

 

 

Power off the device. 

Step 1

 

Stabilize the device, unscrew the U-shaped derrick 

Step 2

nut and take out the U-shaped derrick screw. 

 

Take out the device, disassembling ends. 

Step 3

Wall-mounted Device Mounting

 

 

Use 4 M6 screws to install the clamp board as 

Step 1

shown in the figure below on the device backboard. 

 

 

Align the other clamp board with the hole center 

Step 2

line of the installed clamp board, then place the 
support pipe to align the hole center of the two 
clamp boards. When the two clamps are docking, 
you can choose 15° or 90° installation angle. 

 

 

Pass the M6 long screw through the hole where the 

Step 3

clamp boards are docked and the support pipe, and 
tighten the corresponding M6 nut. 

 

 

Pass the M6 screw through the location hole of the 

Step 4

clamp board. The size of location hole of the clamp 
board is as shown below. 