background image

 

 

 

 

 

SILVER 800 & SILVER 1000 INBUILT 

ZERO CLEARANCE BOX SUPPLEMENT INSTRUCTIONS 

 

MUST BE IN CONJUNCTION WITH THE INSTALLATION MANUAL FOR THE 

SILVER 

800 AND 

SILVER 

1000 MODELS. 

 

 

 

TESTED IN ACCORDANCE WITH AS/NZS 4013:2014 and AS/NZS 2918. 

Please read through this manual thoroughly before installing and starting your free-standing 

appliance. 

Keep these instructions for future reference. 

 

 

 

 

 

 

 

 

Summary of Contents for SILVER 1000

Page 1: ...ONJUNCTION WITH THE INSTALLATION MANUAL FOR THE SILVER 800 AND SILVER 1000 MODELS TESTED IN ACCORDANCE WITH AS NZS 4013 2014 and AS NZS 2918 Please read through this manual thoroughly before installing and starting your free standing appliance Keep these instructions for future reference ...

Page 2: ...Lacunza Silver 800 1000 Zero Clearance Box Assembly Instructions June 12 2022 2 Zero Clearance Parts List Check all the parts are supplied before beginning the assembly ...

Page 3: ...Lacunza Silver 800 1000 Zero Clearance Box Assembly Instructions June 12 2022 3 ...

Page 4: ...ide end frames for the stand first For each end you will use 2 x Stand Horizontal Short Brackets and 2 x Stand Vertical Brackets Lay them out as seen in the image below 1 2 Line up the corners by aligning the holes with the wider fold in the leg and use the 8 x Self Tapping Screws on each hole 1 3 Repeat for the opposite side You should have 2 x Stand Sides ...

Page 5: ...so be used to fix the frame to the floor Ensure the base is secured to the floor using fixings appropriate for the flooring structure The floor must be able to support the weight of the heater flue and fuel load which is approximately 300kg Refer to Step 2 2 to see how the Tabs can be bent out 1 6 This concludes the assembly for the Stand and you can now prepare for the assembly of the Zero Box Yo...

Page 6: ... completed Stand The front of the bottom panel should be flat in line with the front stand face 2 2 Flip up the Top Tabs to stop the Bottom Plate from moving around Ensure you do this on both sides there should be a total of four Top Tabs 2 3 Once the front is lined up and the tabs are bent up secure the Bottom Plate to the Stand by using 6 x Self Tapping Screws ...

Page 7: ... Bottom Panel 2 5 Grab either the RHS LHS Side Panel and slot it into the appropriate sides This is indicated with the circle cut outs on each Side Panel which should be on the bottom side and the three fold edge should be on the front side Note the Side Panels should be placed on the inside of the Bottom Panel 2 6 Screw the lined up holes for the RHS LHS Side Panel as shown below you will need 5 ...

Page 8: ...les and use 9 x Self Tapping Screws Use the circle cut outs in the Back Panel to pull the sheet towards you which should help when you are inserting the Self Tapping Screws Again don t tighten the Self Tapping Screws until the Top Panel has been placed 2 9 You can now place the Top Panel on the top All the folds should sit on the outside of the Side Panels and the Back Panel ...

Page 9: ...pping Screws for the sides A total of 10 x Self Tapping Screws and 3 x Self Tapping Screws If you are installing for the Silva 800 then go to Step 4 before continuing Once the Top Panel is on tighten all the screws 2 11 You can then add the Back Bracket to the Back Panel The heater will stop when inserted up to the Back Bracket Use 4 x Self Tapping Screws to attach the Back Bracket ...

Page 10: ...ped hook is fixed to the 300mm Flue Outer Casing You will need 3 x Self Tapping Screws for each Flue Bracket A total of 6 x Self Tapping Screws The 200mm Flue slides through the top of the Zero Clearance Box and sits above the heater resting on the Flue Brackets The 200mm Flue must be sealed with a flexible sealant around the top of the Zero Clearance Box to stop heater air from coming into the ch...

Page 11: ...SILVER 1000 to SILVER 800 4 1 If you are installing the Silver 1000 then you are completed with assembly If you are installing for the Silver 800 you will need to assemble the 2 x Side Fill Ins before tightening the Top and Side Panels There are four slots for each Side Fill In at the top and bottom ...

Page 12: ...Lacunza Silver 800 1000 Zero Clearance Box Assembly Instructions June 12 2022 12 Completed Zero Clearance Box with Stand for Lacunza Silver 800 1000 ...

Page 13: ... be made of a heat resistant material 6 Underside mantle shelf shall be no closer than 550mm from the top of the appliance hot air outlet the mantle shelf shall extend no further than 250mm into the room 7 Underside mantle key shall be no closer than 500mm from the top of the appliance hot air outlet the mantle key shall extend no further than 25mm into the room 8 Mantle uprights shall be no close...

Page 14: ...sistant material 6 Underside mantle shelf shall be no closer than 550mm from the top of the appliance hot air outlet the mantle shelf shall extend no further than 250mm into the room 7 Underside mantle key shall be no closer than 500mm from the top of the appliance hot air outlet the mantle key shall extend no further than 25mm into the room 8 Mantle uprights shall be no closer than 150mm from the...

Page 15: ...Lacunza Silver 800 1000 Zero Clearance Box Assembly Instructions June 12 2022 15 Clearance Diagrams Silver 800 ...

Page 16: ...Lacunza Silver 800 1000 Zero Clearance Box Assembly Instructions June 12 2022 16 Silver 1000 ...

Reviews: