RELION® PRODUCT FAMILY

Grid Automation

REC615 and RER615

Engineering Manual

Summary of Contents for RELION Series

Page 1: ...RELION PRODUCT FAMILY Grid Automation REC615 and RER615 Engineering Manual...

Page 2: ......

Page 3: ...Document ID 1MRS757810 Issued 2018 08 31 Revision C Product version 2 0 Copyright 2018 ABB All rights reserved...

Page 4: ...this document is furnished under a license and may be used copied or disclosed only in accordance with the terms of such license Trademarks ABB and Relion are registered trademarks of the ABB Group Al...

Page 5: ...ted and communicate data and information via a network interface which should be connected to a secure network It is the sole responsibility of the person or entity responsible for network administrat...

Page 6: ...concerning electrical equipment for use within specified voltage limits Low voltage directive 2014 35 EU This conformity is the result of tests conducted by ABB in accordance with the product standar...

Page 7: ...lways be followed The frame of the protection relay has to be carefully earthed When the plug in unit has been detached from the case do not touch the inside of the case The relay case internals may c...

Page 8: ......

Page 9: ...ing connectivity packages 25 Installing connectivity packages by using the connectivity package installer 25 Installing connectivity packages by using Update Manager 25 Activating connectivity package...

Page 10: ...nfiguration parameters 70 Connections and variables 71 Hardware channels 71 Online monitoring 72 Validation 73 Validation when creating an application configuration 73 Validation on demand 73 Validati...

Page 11: ...event filtering 104 Starting HMI event filtering 104 Setting visibility of HMI events 104 Searching events 105 Saving event filter configuration 105 Section 7 IEC 61850 communication engineering 107...

Page 12: ...engineering LED connections 131 Reengineering in the Parameter Setting tool 135 Reengineering in the IEC 61850 Configuration tool 136 Reengineering in the Communication Management Tool 136 Checking an...

Page 13: ...and other supported protocols 1 2 Intended audience This manual addresses system and project engineers involved in the engineering process of a project and installation and commissioning personnel wh...

Page 14: ...77B CCE64F6FC8D0 V2 EN Figure 1 The intended use of documents during the product life cycle Product series and product specific manuals can be downloaded from the ABB Web site http www abb com relion...

Page 15: ...esult in degraded process performance leading to personal injury or death Therefore comply fully with all warning and caution notices 1 4 2 Document conventions A particular convention may not be used...

Page 16: ...LPDOC3 3I 3 67 1 3 Three phase directional overcurrent protection low stage instance 4 DPHLPDOC4 3I 4 67 1 4 Three phase directional overcurrent protection high stage instance 1 DPHHPDOC1 3I 1 67 2 1...

Page 17: ...tance 2 WPWDE2 Po 2 32N 2 Wattmetric based earth fault protection instance 3 WPWDE3 Po 3 32N 3 Harmonics based earth fault protection instance 1 HAEFPTOC1 Io HA 1 51NHA 1 Multifrequency admittance bas...

Page 18: ...ster trip instance 1 TRPPTRC1 Master Trip 1 94 86 1 Master trip instance 2 TRPPTRC2 Master Trip 2 94 86 2 Multipurpose protection instance 1 MAPGAPC1 MAP 1 MAP 1 Multipurpose protection instance 2 MAP...

Page 19: ...I O ES 3 Earthing switch indication instance 4 ESSXSWI4 I O ES 4 I O ES 4 Earthing switch indication instance 5 ESSXSWI5 I O ES 5 I O ES 5 Earthing switch indication instance 6 ESSXSWI6 I O ES 6 I O...

Page 20: ...ergy measurement instance 2 PEMMXU2 P E 2 P E 2 Single phase power and energy measurement instance 1 SPEMMXU1 SP SE 1 SP SE 1 Single phase power and energy measurement instance 2 SPEMMXU2 SP SE 2 SP S...

Page 21: ...3 UDFCNT3 UDCNT 3 UDCNT 3 Analog value scaling instance 1 SCA4GAPC1 SCA4 1 SCA4 1 Analog value scaling instance 2 SCA4GAPC2 SCA4 2 SCA4 2 Analog value scaling instance 3 SCA4GAPC3 SCA4 3 SCA4 3 Analog...

Page 22: ...n IEC 61850 IEC 60617 IEC ANSI Logging functions Disturbance recorder RDRE1 DR 1 DFR 1 Fault record FLTRFRC1 FAULTREC 1 FAULTREC 1 Section 1 1MRS757810 C Introduction 14 REC615 and RER615 Engineering...

Page 23: ...l Reusing configurations from older protection relay versions using the Configuration Migration tool Communication management IEC 61850 station communication engineering is done using the internal IEC...

Page 24: ...anizing users regarding their rights profiles and passwords to use different tools and functions in the tools Defining allowed activities for user profiles to use tools in PCM600 Once the engineering...

Page 25: ...from the structure of the primary equipment in the substation In PCM600 it is possible to set up a hierarchical structure of five levels for the device identification Project Substation name of the s...

Page 26: ...ended functional application The standard configurations also have selectable software options which are selected when ordering the protection relay Some of the software options are related to the pro...

Page 27: ...50 Configuration tool to PCM IEC 60870 5 101 104 GUID C45BA34E 9036 4AE3 A677 5B9B47168992 V1 EN Figure 3 Protection relay engineering workflow proposal based on practical experience and dependencies...

Page 28: ...djusted with the Parameter Setting tool Single line diagram configuration in Graphical Display Editor It is possible to create a single line diagram for the switching devices in the bay Measurements c...

Page 29: ...tically when writing a relay configuration where changes have been made It is not possible to communicate with the protection relay during restart 1MRS757810 C Section 2 Relay engineering process REC6...

Page 30: ...22...

Page 31: ...e ability to export the configuration of the devices or an entire substation in a standard file format which enables station engineering in separate IEC 61850 System Configuration tools A PC with PCM6...

Page 32: ...ng range access rights and visibility of the parameters In addition it contains code which allows software packages that use the connectivity package to properly communicate with the protection relay...

Page 33: ...ckage RE_6xx Ver n msi installer n version number 3 To install the connectivity package follow the steps in the connectivity package installation wizard 3 2 1 2 Installing connectivity packages by usi...

Page 34: ...eft column to access the installed connectivity packages 2 Browse the tree structure to find the correct product 3 Select the connectivity package version from the drop down list beside the product na...

Page 35: ...By default the IEC 61850 version of PCM600 is Edition 1 The protection relay s IEC 61850 version is by default Edition 2 With PCM600 it is possible to do various tasks Open existing projects Import pr...

Page 36: ...etween the IED object and the physical IED technical key GUID 653F00D4 EA39 45A2 BF0D 5BF2B15F3BEA V3 EN Figure 7 Reboot suggestion Ensure that the IED object in PCM600 has the same IP address as the...

Page 37: ...els beginning with the station as the highest level The technical key is automatically generated based on the rules and type specifications of IEC 61346 and the extended definitions assigned for subst...

Page 38: ...project J1 voltage level from 20 to 30 kV Q03 the third bay in the voltage level A1 first IED in the bay Q03 3 4 2 Setting the technical key The maximum length of technical key is 28 characters for E...

Page 39: ...62 9F2A 6F6E6E1C5001 V3 EN Figure 9 PCM600 Setting the technical key on the IED level A dialog box opens to inform about the technical key concept 1MRS757810 C Section 3 PCM600 tool REC615 and RER615...

Page 40: ...78 728D64662578 V1 EN Figure 10 Technical key information 2 Click OK The technical key is read from the IED and the Set Technical Key dialog box opens Section 3 1MRS757810 C PCM600 tool 32 REC615 and...

Page 41: ...4 Click OK to confirm the selection It is not possible to set a user defined name or select the Technical key in IED if the value is the same as already given to another IED object in the PCM600 proje...

Page 42: ...al keys of the IEDs in PCM600 project are configured for each protection relay to match the technical keys of the physical IEDs For successful protection relay engineering and usage check the workstat...

Page 43: ...rameter 3 6 IED Update The firmware update tool is used for patching the IED firmware and for adding or replacingadditionallanguagestotheIED UpdatepackagesareprovidedbyCustomer Support The update tool...

Page 44: ...PCM600 IED Configuration Configuration Authorization Remote Update to be able to update remotely If the IED is in local control mode remote update proceeds only after a confirmation is received from t...

Page 45: ...nd click OK GUID AF43F861 54EB 4F5E B745 38994F6A423A V1 EN Figure 13 Selecting the network interface controller 4 When updating remotely wait for 30 seconds for the local user confirmation before pro...

Page 46: ...8465323 V1 EN Figure 14 Waiting for local user confirmation with remote update GUID 31FD0CB0 CFBC 48AB BF96 D3F9436DBDEE V1 EN Figure 15 Completing the update Section 3 1MRS757810 C PCM600 tool 38 REC...

Page 47: ...Project window is displayed 3 Click Projects on my computer 4 Click New Project 5 If there are currently projects or object tools open a confirmation dialog box opens Click Yes to close the open proj...

Page 48: ...Description box 8 Click Create PCM600 sets up a new project that is listed under Projects on my computer 4 2 Building the plant structure Building a plant structure is useful when a complete grid wit...

Page 49: ...ame Rename the levels in the Object Properties view 4 3 Inserting an IED The context menu or the Object Types view shows the available IEDs that can be inserted on the bay level into the plant structu...

Page 50: ...D online the protection relay must be connected to PCM600 When the protection relay is already connected to PCM600 PCM600 can read the order number directly from the relay It is possible to read the f...

Page 51: ...6D15745E7 V3 EN Figure 19 Selecting the protection relay type 2 On the Configuration mode selection page select Online Configuration and click Next 1MRS757810 C Section 4 Setting up a project REC615 a...

Page 52: ...Figure 20 Configuration mode selection 3 On the Communication protocol selection page select the communication protocol from the IED protocol list and click Next Section 4 1MRS757810 C Setting up a p...

Page 53: ...On the IEC61850 communication protocol page select the port from the Port list If the rear port is selected type the correct IP address of the physical protection relay to be configured to the IP add...

Page 54: ...n configuration is now defined 5 Click Next to scan read the order code of the protection relay 6 On the Order code detection page click Next GUID C7A331F8 1F10 4D6C 906F FFC8578B3555 V3 EN Figure 23...

Page 55: ...ration to import any existing example configuration Click Browse to select the pcmi pcmt file that has the example configuration Select Standard Configuration to generate a default configuration GUID...

Page 56: ...ed when adding the first protection relay to the plant structure After the initial selection all protection relays in the plant structure use the selected version either Edition 1 or Edition 2 9 The S...

Page 57: ...hat PCM600 has turned online the IED that was inserted to the bay level Data cannot be scanned from the protection relay and proceeding is prevented if the IED is not online or if the IP address is no...

Page 58: ...nfiguration and click Next Setting up an IED in the offline mode is similar as in the online mode however with the offline mode it is not necessary to type the correct IP address in the Communication...

Page 59: ...guration 5 On the Version Selection page select the IEC 61850 version and click Next to generate the functions 6 The Setup Complete Page shows the summary of the IED type version IP address and the se...

Page 60: ...ed in the plant structure 1 In the Plant structure view select the bay right click point to New and select Create from template The Create New Object from Template dialog box opens GUID A5D22ADA 02A5...

Page 61: ...emplate from the selection window click Import Template To insert the selected IED to the bay click Create It is possible to insert more than one IED from the Create New Object from Template dialog bo...

Page 62: ...tting the IED IP address in a project The IP address and subnet mask of the IED object in PCM600 must match the front and rear port of the protection relay physical IED to which the PC is connected Th...

Page 63: ...ID BAB14777 F3F3 4112 921F 9F22D5A66DFC V2 EN Figure 32 Alternative 1 Setting the IP address on the first wizard page 1MRS757810 C Section 4 Setting up a project REC615 and RER615 55 Engineering Manua...

Page 64: ...enu select Object Properties Object Properties dialog box is opened 3 Type in the IP address to the IP Address row 4 5 COM600S project The 615 series connectivity package supports SAB600 A 615 series...

Page 65: ...et range as the front port GUID 6B209BB8 F07E 4414 B404 EA33CEB71DB2 V1 EN Figure 34 Communication port options Check that the settings are correct to ensure successful configuration access to the rel...

Page 66: ...re 35 Creating a PCM600 project including several IEDs 2 Export the SCD file from PCM600 In the Plant structure view select the substation right click and select Export Section 4 1MRS757810 C Setting...

Page 67: ...le from PCM600 and importing it to SAB600 3 Import the SCD configuration into the SAB600 project In the Project Explorer view right click the IEC61850 OPC Server object and select SCL Import 1MRS75781...

Page 68: ...nto the SAB600 project 4 In the SCL Import view click Select File to select the SCD file exported from PCM600 GUID 6F47B4AD B956 4F77 A6A2 DE6F4A71D607 V2 EN Figure 38 Creating a new IED into SAB600 p...

Page 69: ...efault the WHMI must be accessed from a Web browser using the HTTPS protocol 1 To enable the WHMI select Main menu Configuration HMI Web HMI mode via the LHMI 2 Reboot the relay for the change to take...

Page 70: ...I 2 Use the IED Users tool in PCM600 to change the passwords This tool cannot be used to add or change users GUID DF4E526E 401B 47A4 B002 2B67DCB79776 V1 EN Figure 39 Changing the password using the I...

Page 71: ...n twice GUID 0F5E5C0E 30AF 4025 8AE0 462A05561772 V1 EN Figure 41 User login If the PCM600 authentication has been enabled in PCM600 System Settings a relay user can be linked to the current PCM600 us...

Page 72: ...61850 version Edition 1 of an IED to Edition 2 the configuration has to be written to the IED from a PCM600 project that has the IEC 61850 version Edition 2 A dialog box notifies on the difference of...

Page 73: ...unction blocks which are mandatory and thus cannot be removed from the relay configuration by removing them from the Application Configuration Other function blocks are not mapped as logical nodes for...

Page 74: ...ent function block types are shown in the Object Types view Function block data can be modified with the Application Configuration tool User defined names can be given for function blocks and signals...

Page 75: ...order 13 Cycle time 14 Instance number 5 1 2 Signals and signal management The function block has a set of input and output signals The placement of function block signals is from left to right Input...

Page 76: ...e time Instance number Each time a new function block is inserted these parameters are shown in the Function Block Instance dialog box in the Application Configuration tool The three parameters are se...

Page 77: ...cally in the Application Configuration tool but the execution order can also be set manually If the automatically calculated value causes the function to be executed one task cycle time after the othe...

Page 78: ...k GUID 0C12B88A 0ABE 49DE 9A44 05D213D04922 V1 EN Figure 46 Feedback loop situation with manually fixed execution order for NOT port Execution number can be changed by right clicking the function and...

Page 79: ...tically removes the orphan variables which are not connected to any destination Connection validation A connection is only useful or even possible between two signals of the same base attribute type G...

Page 80: ...hannel is requested This prevents using the same hardware binary output channel twice 5 1 8 Online monitoring The online monitoring enables the continuous monitoring of the signal or channel values in...

Page 81: ...ample from a binary output to an analog input 5 1 9 2 Validation on demand The validity of an application configuration can be checked by clicking Validate Configuration in the toolbar The Application...

Page 82: ...t the writing 5 1 10 Configuration load calculation Connectivity package calculates an estimated application configuration load every time it is saved in the Application Configuration tool or written...

Page 83: ...arger scale The calculation result is only visible in PCM600 output window inside Logging tab GUID 98B74959 AAEC 449F 8973 09E1F4A6010F V1 EN Figure 50 Configuration load result an example of nearby m...

Page 84: ...on relay s parameters are set using the WHMI instead of PCM600 The relay settings engineered with PCM600 can be exported to XRIO files and imported to the WHMI The WHMI can be used to write the settin...

Page 85: ...the setting tree 5 3 Signal Matrix tool The Signal Matrix tool is used to make cross references between the physical I O signals and function blocks and for the GOOSE signal input engineering The Appl...

Page 86: ...different function blocks in the Application Configuration tool the connection appears as glue logic in Signal Matrix A binary output channel can only be activated from one function block output If it...

Page 87: ...ts Functions GOOSE 5 4 Load Profile tool Load Profile tool is used for reading load profile records of COMTRADE format from a protection relay clearing old records and viewing records via an external...

Page 88: ...button in the tool The Load Profile tool runs in the same process as PCM600 but in a separate window Multiple instances of the tool can be run at the same time Any open tool instances are closed witho...

Page 89: ...9699D V1 EN Figure 55 Load Profile tool By default the Load Profile tool uses the PCMDataBases LPR directory as a saving target directory 1MRS757810 C Section 5 Protection and control engineering REC6...

Page 90: ...otection relay to a temporary folder C Temp LoadProfileTool on the local machine In this temporary folder the target file name is constant and loading again overwrites the file An unsaved record is de...

Page 91: ...F1 83C3 7AA8087C569C V1 EN Figure 57 Information fields 5 5 Fault Record tool The Fault Record tool is used for reading the fault records from the protection relay and it is included in the connectivi...

Page 92: ...en PCM600 is closed The Fault Record tool is a connectivity package tool The main functionality is divided into three parts reading the fault record parameters from the protection relay displaying the...

Page 93: ...w record details Save Click Save to save the fault records on the local machine as txt file Clear Record can be cleared from either the Fault record tool or the protection relay or both Before deletin...

Page 94: ...ixels Detailed instructions are shown in PCM600 documentation 5 6 1 Starting IED Compare Start IED Compare in the context menu in plant structure 1 In the PCM600 plant structure right click Substation...

Page 95: ...Each configuration group can be expanded or collapsed by clicking the plus or minus button next to it in the result grid The reports must be read from left to right row wise 1MRS757810 C Section 5 Pr...

Page 96: ...st mode Test mode Description Protection BEH_BLK Normal mode Normal operation FALSE IED blocked Protection working as in Normal mode but ACT configuration can be used to block physical outputs to proc...

Page 97: ...ons some of PTRC s might also be used for signalling purposes GOOSE and blocking and interlocking via IO The physical outputs to process can be blocked with IED blocked and IED test and blocked modes...

Page 98: ...ST BEH_BLK AND B1 B2 O AND B1 B2 O NOT IN OUT NOT IN OUT FALSE X120_BI3_CB_OPENED X120_BI2_CB_CLOSED CBXCBR1_ENA_CLOSE TRUE CBXCBR1_AU_OPEN CBXCBR1_AU_CLOSE CBXCBR1_OPENPOS CONTROL_LOCAL CONTROL_REMOT...

Page 99: ...ngle line diagram is modelled according to the IEC 61850 standard in the Graphical Display Editor 6 1 1 Diagrams in Graphical Display Editor The Graphical Display Editor is used for various tasks Crea...

Page 100: ...is empty when no page exists for the protection relay A default single line diagram presentation is displayed if standard configurations are used Additional single line diagram HMI display pages can...

Page 101: ...tandard or IEC standard The standard is selected from the list located on top of the window When changing to another library standard Graphical Display Editor changes the symbols according to the sele...

Page 102: ...position Truck Bad faulty position In feeder Out feeder Current transformer Voltage transformer Earth symbol Motor Generator Power transformer with two windings Fuse Button 6 1 1 4 HMI display raster...

Page 103: ...dling The display switches when text is selected in a display of 22 x 9 columns x rows One display box holds one character A text element must be placed in the position of the display The name and the...

Page 104: ...ter box GUID 3EA8E776 CF57 464F AE99 168AB9084369 V1 EN Figure 66 Select button 2 Right click the select button symbol point to Select Input Signal and select the input signal from the list Section 6...

Page 105: ...s Unit text specifies the default text used for the measurement s unit If the Unit text is empty in the Graphical Display Editor no unit is shown If the Unit text is not empty the unit in the protecti...

Page 106: ...ween one busbar junction point and the corresponding symbol or junction point 6 1 1 10 Adding symbols into a display page 1 Prepare the body of the single line diagram by locating symbols to the wante...

Page 107: ...pparatus symbols are placed lines can be drawn to create links 1 To draw a line point to the center of the connection point which is visible in two circles at the end points of a line 2 Drag the point...

Page 108: ...epresents 6 1 2 1 Linking process objects To describe a process object within an IED it needs to be established in the application configuration configured when given the parameters by the Parameter S...

Page 109: ...ignal A list of the engineered measurement application function blocks opens 4 Select the measurement application function block that corresponds to the selected symbol GUID 83D3B54C BF87 4F27 A5C0 02...

Page 110: ...the single line diagram 2 Place the apparatus transformer and other symbols that are needed for the single line diagram into the raster boxes 3 Add Junction points where needed 4 Link the apparatus sy...

Page 111: ...import The single line diagram templates enable the reuse of the single line diagram created in the Graphical Display Editor tool The single line diagram can be exported as a template and the same te...

Page 112: ...are selected click Import to import the display page Multiple pages can be selected for the Import function 6 3 HMI event filtering HMI Event Filtering is a tool that helps in configuring visibility...

Page 113: ...using predefined search strings 1 Click the search text box shown on top of the event tree view A drop down list is shown with predefined search strings 2 Select the event name to be shown in the even...

Page 114: ...106...

Page 115: ...tion 1 and Edition 2 Logical Nodes Function IEC 61850 Logical device Logical nodes in Ver 5 0 FP1 Logical nodes in Ver 5 0 or older Protection Protection LLN0 Protection LD0 LLN0 LPHD LINF LDEV LLN0 L...

Page 116: ...ased earth fault protection MFADPSDE LD0 MFADPSDE MFADRDIR Non directional cross country earth fault protection using calculated Io EFHPTOC LD0 EFHPTOC EFHPTOC Negative sequence overcurrent protection...

Page 117: ...WI CBCILO CBXCBR Disconnector control DCXSWI CTRL DCCSWI DCCILO DCXSWI DCCSWI DCCILO DCXSWI Disconnector position indication DCSXSWI CTRL DCSXSWI DCSXSWI Earthing switch indication ESSXSWI CTRL ESSXSW...

Page 118: ...VMMXU RESVMSTA Phase sequence voltage measurement VSMSQI LD0 VSMSQI VSMSQI Three phase power and energy measurement PEMMXU LD0 PEMMXU PEMMTR PEAVMMXU PEMAMMXU PEMIMMXU PEMMXU PEMMTR PEMSTA Single phas...

Page 119: ...inimum pulse timer TPSGAPC TPSGAPC TPSGAPC Minimum pulse timer TPMGAPC TPMGAPC TPMGAPC Pulse timer PTGAPC PTGAPC PTGAPC Time delay off TOFGAPC TOFGAPC TOFGAPC Time delay on TONGAPC TONGAPC TONGAPC Set...

Page 120: ...0 XAGGIO130 AIM X130 5 VT 2RTD and 1mA X130 AIM RTD LD0 XARGGIO130 XARGGIO130 SIM X130 sensor input module X130 SIM LD0 XSGGIO130 XSGGIO130 SIM X130 3Is_3Us with sensitive Io X130 SIM LD0 XSGGIO130 XS...

Page 121: ...These signals are identified through the logical nodes representing the functions All signal information for commands and monitoring are available in logical nodes Whenever a function block is instant...

Page 122: ...D as a receiver of a GOOSE message How the GOOSE input signals are handled must be defined in the device s application configuration The SCL data generated by the IEC 61850 Configuration tool or IET60...

Page 123: ...configuring one specific IED The CID file contains the complete configuration description of one specific IED This includes the configured IED name communication part data sets and all control blocks...

Page 124: ...possible to export other SCL file types 2 Horizontal and vertical communication is configured using the station configuration tool for example IEC 61850 Configuration tool or IET600 3 SCL files are im...

Page 125: ...en a complete station is exported as a SCD file 7 3 1 Exporting SCL files from PCM600 A pre condition for exporting SCL files from PCM600 is that all IEDs in the project must be engineered in PCM600 T...

Page 126: ...t the location to store the file and name it 4 Click Save The SCL Export Options dialog box opens GUID 632A916F B7FE 4EF4 B29A 6A2A5B9FBC4D V1 EN Figure 80 IEC 61850 selecting the SCL export option 5...

Page 127: ...x opens 3 From the Save as type list select the type of file to export Configured IED description cid for the IEC 61850 structure as needed for the IED at runtime IED capability description icd for th...

Page 128: ...8 V1 EN Figure 84 SCL export options 7 Click Export 7 3 2 Engineering vertical and horizontal communication For IEC 61850 engineering a separate system configuration tool is needed to be used with PCM...

Page 129: ...ved of the following CDC types SPS SPC ACD ACT DPS DPC INC INS ENC and ENS 3 3 Configure additional Report Control Blocks when needed for each data set used for vertical communication 3 4 Link the IED...

Page 130: ...ls menu select Options and click IEC 61850 Configuration 2 Clear the option IED 61850 configuration engineering mode enabled and click OK GUID 3C811FF5 97F7 4703 81EE A0C4AC30C8D0 V1 EN Figure 85 Enab...

Page 131: ...e Generic IEC 61850 IED is used to integrate these kinds of IEDs into the plant structure for example Click Ignore PCM Object Type to update the IED object s in PCM600 from the IED type s in the SCD f...

Page 132: ...433BC9876 V2 EN Figure 88 Common write menu The engineered data is written to the IED when executing a common Write to IED operation Section 7 1MRS757810 C IEC 61850 communication engineering 124 REC6...

Page 133: ...ates the IED object s in PCM600 from the IED type s in the SCD file discarding whether or not the IED type s in the SCD file matches the IED object s in PM600 Ignore Substation Section does not import...

Page 134: ...elect GOOSE to update the GOOSE configuration part in the IED Select Process bus IEC 61850 9 2 to update the IEC 61850 9 2 configuration part in the IED 2 Select whether or not to update the configura...

Page 135: ...ntents of an existing IED configuration and enables using it with the latest product version Backup creation Automatic Configuration Migration Reengineering ACT PST CMT Write to IED ICM report review...

Page 136: ...ectivity package version Source version Target version PCM600 2 9 Ver 2 0 Ver 1 1 Ver 2 0 8 3 Backup creation While starting IED Configuration Migration a backup is created automatically The backup pr...

Page 137: ...and do not need to be reengineered The migration takes a few minutes The PCM600 output window contains valuable information from different parts of the migration such as successfully imported paramete...

Page 138: ...94 Saving and printing from the tool bar Save the IED configuration migration report for later use as PCM600 does not save it automatically 8 5 Reengineering the migrated configuration 8 5 1 Reengine...

Page 139: ...11 for the IEC 61850 Edition 1 vs Edition 2 mapping 8 5 1 1 Example of reengineering LED connections LED functionality has changed in Ver 2 0 For example the color of the LEDs when an alarm is trigge...

Page 140: ...migration 2 Delete old output blocks shown in red 3 Drag new LED blocks from the Object Types pane on the left to the Application Configuration pane LED function blocks can be found under Local HMI Se...

Page 141: ...nnect the inputs to the correct LED function blocks by dragging from the variable or OR function block output to the input of the LED function block Rearranging may be required to fit everything on th...

Page 142: ...GUID 78AC7B5D 1F29 4242 9E6C 8F14F94951A7 V1 EN Figure 98 Connecting LED inputs to correct LED blocks Section 8 1MRS757810 C Configuration migration 134 REC615 and RER615 Engineering Manual...

Page 143: ...figuration 8 5 2 Reengineering in the Parameter Setting tool Parameter values remain unchanged for all the functions listed in Versioned Functions and Hardwares list Parameter values remain unchanged...

Page 144: ...g DNP3 points If DNP3 is used the migrated DNP3 point list should for most part correspond to the configuration made in the old IED 1 Check the point list and verify that all the point types correspon...

Page 145: ...ommunication Management tool 3 Change the possible changed point addresses to match the master address by using a user defined address instead of the default address 4 Adjust possible missing points p...

Page 146: ...138...

Page 147: ...mon format for transient data exchange for power systems Defined by the IEEE Standard Connectivity package A collection of software and information related to a specific protection and control IED pro...

Page 148: ...stantiated IED description Instance Identical protection function blocks available in a standard configuration By setting the application specific parameters of an instance a protection function stage...

Page 149: ...ion configuration language defined by IEC 61850 SMT Signal Matrix tool in PCM600 SNTP Simple Network Time Protocol Subnet mask A set of four numbers used to create IP address numbers that are used onl...

Page 150: ...142...

Page 151: ...143...