background image

9

© Copyright 2020 Zoeller

®

 Co. All rights reserved.

Outdoor Prepackaged System Installation Instructions

  1.  Review the drawing in Fig. 3 on page 8 and the actual system to 

become familiar with the components in the packaged grinder pump 

system.  Review where the unit will be installed.  Determine where 

the power feed, inlet pipe, and discharge pipe will be located.

  2.  Remove the unit from packing.  Prepackaged outdoor systems are 

preassembled at the Zoeller Company and require a minimum of 

field assembly work.  Float switches are set and tethered for proper 

operation from the Factory.  Systems using an automatic unit, WD 

or WH series, have an integral “on/off” float switch.  See Fig. 4 

on page 5 for adjustment instructions.  The alarm switch should 

be located 3” above the pump “on” level.  Three float systems 

used with a control panel are placed at 27”, 24”, and 15” from the 

bottom of the basin.  Four float systems used with a control panel 

are placed at 33”, 27”, 24”, and 15” from the bottom of the basin. 

If the invert location is at or below the level of the float switches, 

contact the factory.  

  3.  Float switches are tied in place for shipping purposes on all model 

prepackaged systems.  Cut the cable tie around each float switch 

bulb or the unit will not operate properly.  Verify that where the 

float switches are set will work for your application. 

 

Verifying 

that the float switches are set properly and will not hang up inside 
the basin is the responsibility of the installing contractor. 

 

4.  Dig a hole for the basin.  The hole should be at least 24” larger in 

diameter than the basin diameter to provide 12” of backfill all around 

and deep enough to provide either 12” of compacted backfill or 6” 

when a concrete pad is required.

  

Note:  Care must be taken when 

excavating in order to avoid underground utilities and disturbance of 
existing structure foundations.  The hole should be located at least ten 
feet from adjacent structures.  Additional distance may be required to 
sufficiently locate the basin outside of the loading area of the adjacent 
structures.

  5.  The location of the inlet hub is determined by the depth of the inlet 

pipe.  The inlet hub must be used with 4” pipe.  It is best to install 

the inlet on the side of the basin opposite the float switches.  To 

install, use a 4” hole saw to drill into the side of the basin at the 

correct elevation.  Center the hub inner diameter with the hole in 

the basin.  Attach the hub to the side of the basin using the sealant 

and hardware provided.

  6.  The bottom of the excavation can now be properly backfilled, 

compacted and leveled.  Set basin in hole.  Ensure the removable 

cover extends above the finished grade line and the grade slopes 

away from the unit.  Backfill and subbase should be 1/8” –3/4” pea 

gravel or 1/8” –1/2” crushed stone.  (Reference basin installation 

instructions included with unit.)  Connect the 4” inlet pipe to the 

inlet hub.  

  7.  Pouring a concrete anchor around system can now be completed.  

Basin should be filled with water when pouring concrete to minimize 

movement of the system.  Backfill around basin with specified media.  

Care should be used to avoid damaging components or leaving voids 

when back filling.  Refer to Basin installation reference guide on 

more specific requirements.

  8.  PVC or HDPE discharge piping is connected to the 2” threaded 

fitting located in the basin sidewall.  Support discharge piping with 

sufficient backfill.

  9.  Connect lift cable to top of pump.  Lower the pump into basin ensuring 

the discharge pipe bracket slides into the disconnect fitting.

 10.

 

Note:  The grinder basin is a sewage holding tank.  Vent connection should 
be installed in accordance with all national, state and local plumbing 
codes.

  11.  Dig a trench for the electrical conduit.  The conduit should be located 

below the frost line.  Follow all applicable electrical codes.

 12.  If using a junction box, connect the electrical conduit and wiring 

according to instructions included in this manual and wiring diagram 

in box.  If a potting kit is provided with the junction box,  follow the 

instructions for sealing the conduit connection to the junction box. 

If a potting kit is not provided, the conduit connection to the junction 

box must be sealed.

 13.  Mount the control panel within sight of the system.  Connect 

float switches and pump cords according to the “Pump Wiring 

Instructions” found later in this manual and located inside the panel 

enclosure.

  14.  Remove any debris from the basin.  Using clean water, check the 

system for proper operation.

 15.  Seal and secure the lid using the proper bolts and sealant when 

using a lid without a formed gasket. 

  16.  Test system for leaks and proper pump operation.
  17.  Record system start up data for future reference.

This set of instructions is for factory prepackaged outdoor grinder systems only.  If this is a field assembled outdoor system 

you can use these instructions as a guideline.  If this is an indoor system then go back to pages 6-7 in this manual that covers indoor systems.

Summary of Contents for 7008

Page 1: ...pportDepartment at 1 800 928 PUMP 7867 Owner s Information Table of Contents Safety Instructions 1 Limited Warranty 2 Preinstallation Checklist 3 General Information 4 Pump Wiring Instructions 5 Typical Indoor Prepackaged System 6 Indoor Prepackaged Installation Instructions 7 Typical Outdoor Prepackaged System 8 Outdoor Prepackaged Installation Instructions 9 Operation 10 Cutter Maintenance 11 Se...

Page 2: ...CIAL CONSEQUENTIAL OR INCIDENTAL DAMAGES OR BREACH OF EXPRESSED OR IMPLIED WARRANTY AND ANY IMPLIED WARRANTY OF FITNESS FOR A PARTICULAR PURPOSE AND OF MERCHANTABILITY SHALL BE LIMITED TO THE DURATION OF THE EXPRESSED WARRANTY Some states do not allow limitations on the duration of an implied war ranty so the above limitation may not apply to you Some states do not allowtheexclusionorlimitationofi...

Page 3: ...ed so that the grinder pump will shut off It is recommended to use rigid pipe and fittings and the pit be 24 in diameter for simplex systems and 36 in diameter for duplex systems or larger 4 Grinderinstallationsshouldbecheckedyearlyfordebrisand orbuildupwhich may interfere with the ON or OFF positions of variable level float control switches Repairandservice otherthancutterassemblymaintenance shou...

Page 4: ...ertight seal Installation of electrical panels conduit and connections should be made by a qualified licensed electrician A UL Listed potting kit P N 10 2350 is available from Zoeller Company 4 When installing a pump with a check valve or a rail system with a check valve you must give the pump case time to fill to help prevent air lock when lowering the unit into the liquid The pump case has an ai...

Page 5: ...g Instructions Installation and checking of electrical circuits and hardware should be performed by a qualified licensed electrician 010415 AUTOMATIC WIRING DIAGRAM 010443 NONAUTOMATIC WIRING DIAGRAM 1 PH FIGURE 4 FIGURE 5 Models WD WH are fully automatic A float switch is included and factory wired in the pump circuit to provide automatic operation once the float switch is secured properly to the...

Page 6: ...CORD SEAL INSPECTION PLATE 3 GROMMET SEAL SWITCH CORD ALARM FLOAT BASIN COVER LIFTING BOLT 16 X 1 4 STEEL 5 16 304 STAINLESS STEEL PUMP PLATE PUMP POWER CORD SILENCE INPUT 1 POWER ON FIELD INSTALLED ALARM 4 RUBBER INLET CAST IRON ADAPTERS OFF 24 NOMINAL TO ALARM PANEL BALL VALVE FIELD INSTALLED GALVANIZED PIPE 1 1 4 X 32 GALVANIZED PIPE 1 1 4 X 12 GRINDER PUMP SINGLE PHASE 2HP 1 1 4 GROMMET SEAL F...

Page 7: ...ould be located in a very low trafficareawithin15 ofthepowerdisconnect Theholeshouldbeat least8 largerindiameterthanthebasininordertoleave4 ofbackfill all the way around the perimeter A minimum of 4 of compacted subbase is also required Backfill and subbase should be 1 8 to 3 4 pea gravel or 1 8 to 1 2 crushed stone Also reference the basin installation instructions included with the unit 6 The 4 ...

Page 8: ...GLASS AFD 1 25 2 Z RAIL 2 CAST IRON CHECK VALVE 3 4 GUIDE RAILS 2 SCH 80 BALL VALVE 2 FLEX BOOT FITTING LOCATION VARIES WITH BASIN DEPTH FLOAT TREE ASSEMBLY 2HP GRINDER PUMP 2 PVC SCH 80 PLBG 1 8 302 STAINLESS STEEL LIFTING CABLE ALARM ON OFF SOLID FIBERGLASS COVER HIGH WATER ALARM OR SIMPLEX CONTROL PANEL FIELD INSTALLED ALARM FLOAT SWITCH MUST OPERATE OFF LOW VOLTAGE TO BE USED WITH QWIK BOX SK3...

Page 9: ...b inner diameter with the hole in the basin Attach the hub to the side of the basin using the sealant and hardware provided 6 The bottom of the excavation can now be properly backfilled compacted and leveled Set basin in hole Ensure the removable cover extends above the finished grade line and the grade slopes awayfromtheunit Backfillandsubbaseshouldbe1 8 3 4 pea gravel or 1 8 1 2 crushed stone Re...

Page 10: ...installed Floats positioned properly Discharge valves open 3 16 vent hole drilled in pipe between check valve and pump Once the above has been verified proceed with the following checks Pump power cables and control floats properly installed and voltage verified Conduit connections to panel and junction box are properly sealed After installing the pump into the containment area with adequate subme...

Page 11: ...rinding both disc and cutter to a 32 micro finish Do not attempt grinding in the field Send parts to a qualified machine shop or return to the factory for repair The disc cutter and shims are a matched set Keep parts together Measure disc before and after resurfacing with micrometer and record measurements 6 After resurfacing the disc and cutter must be flat within 0 001 If the disc has been surfa...

Page 12: ... protective sole shoes and not standing in water Under flooded conditions contact your local electric company or a qualified licensed electrician for disconnecting electrical service to the pump prior to removal Grinder pumps contain oil which becomes pressurized and hot under operating conditions Allow 2 1 2 hours after shut down before servicing pump Condition A Pump will not start or run B Moto...

Reviews: