STEP 1: Remove the connector parts
Remove the bottom connector parts.
STEP 2: Install the clamp
Put the clamp bolts into the
installation holes, and then tighten
the nuts. Maintain the distance
between two clamps used to install
the PV modules about 1m.
STEP 3: Install the PV modules
Insert the PV module into the clamp,
and make sure the module edge
touch to the EPDM closely and then
tighten the nut with uniform torque
values using a q qualified torque
wrench. Ensure the module is firmly
secured.
*NOTES:
Other mounting configurations can be used. However, failure to comply with the above recommendations will
result in a lowering of the load handling capabilities below the empirical value, and product failure as a result of an
overload situation will not be covered by the ZNSHINE SOLAR warranty.